What management said about Q2 FY2026, from the documents filed with the SEC on 6 August 2026: press release. Guidance figures: 5 raised, 3 kept. The quarter’s numbers.

Key takeaways

  • Revenue and EBITDA rose year on year: Revenues were $5.73 billion in the quarter, up 24% from $4.64 billion, and Consolidated Adjusted EBITDA was $1.80 billion, up 27%. Six-month revenues were $11.60 billion and EBITDA $4.14 billion, up 26%. Source
  • Net income swung on derivative values: Net income attributable to Cheniere was $3.07 billion for the quarter against $1.63 billion a year earlier, and a $0.43 billion loss for six months. Management tied the change mainly to fair value changes on IPM agreements. Source
  • Cargo exports rose 19% in quarter: 184 cargoes were exported in the quarter versus 154 a year earlier, and 371 in six months versus 322. Volumes were 672 TBtu for the quarter, up 22%, and 1,360 TBtu for six months, up 17%. Source
  • Train 6 reached substantial completion: Midscale Train 6 of the CCL Stage 3 Project reached substantial completion in June 2026, after Train 5 in March. Trains 1-6 are now operational at CCL Stage 3. Source
  • Higher margins per MMBtu on deliveries: Management said Consolidated Adjusted EBITDA rose on higher total margins on LNG delivered, mainly from higher volumes recognized in income, and on higher margins per MMBtu delivered. Source
  • Liquidity stood at $7.48 billion: Total available liquidity at June 30 was $7.48 billion, made up of $1.10 billion of cash and cash equivalents and $5.96 billion of available credit facility commitments. Source
  • Buybacks of $550 million in quarter: Cheniere repurchased about 2.2 million shares for $550 million in the quarter and 4.9 million shares for $1.1 billion in six months. Treasury shares were 71.7 million at June 30, against 66.8 million at year end. Source

“highlighted by the substantial completion of Midscale Train 6 at the CCL Stage 3 Project, and our further progress towards an FID of Phase 1 of the SPL Expansion Project”

Jack Fusco, Cheniere’s Chairman, President and Chief Executive Officer

Guidance

AreaPeriodFigureAgainst last quarter
Consolidated Adjusted EBITDA Sourcefull year 2026$7.90 billion - $8.40 billionRaised from $7.25 billion - $7.75 billion
Distributable Cash Flow (Cheniere) Sourcefull year 2026$5.30 billion - $5.80 billionRaised from $4.75 billion - $5.25 billion
Consolidated Distributable Cash Flow Sourcefull year 2026$6.40 billion - $6.80 billionRaised from $5.8 billion - $6.3 billion
Net income attributable to Cheniere Sourcefull year 2026$1.6 billion - $2.0 billionRaised from $0.1 billion - $0.6 billion
LNG production Sourcefull year 202653-54 million tonnesRaised from 52-54 million tonnes
Maintenance capital expenditures Sourcefull year 2026$0.2 billionKept
CCL Stage 3 Midscale Train 7 substantial completion Sourcefall 2026fall of 2026Kept
CCL Midscale Trains 8 & 9 substantial completion Source2H 20282H 2028Kept

What changed from last quarter

  • Guidance raised: Full-year 2026 Consolidated Adjusted EBITDA guidance raised to $7.90-$8.40 billion from $7.25-$7.75 billion. Source
  • Guidance raised: Full-year 2026 Distributable Cash Flow guidance raised to $5.30-$5.80 billion from $4.75-$5.25 billion. Source
  • Guidance raised: LNG production forecast range narrowed upward to 53-54 million tonnes from 52-54 million tonnes. Source
  • New: SPL Expansion Project first phase: EPC contract with Bechtel signed in May 2026, with early engineering and procurement under a limited notice to proceed. Source
  • New: FERC authorized an increase of about 5 mtpa in aggregate LNG production capacity for CCL Stage 3 and CCL Midscale Trains 8 & 9 in June 2026. Source
  • New: Cheniere Revolving Credit Facility extended one year and increased by $500 million to $1.75 billion; CCH working capital facility restated and cut to $1.0 billion. Source
  • New: Cheniere Partners issued $1.0 billion of 5.350% notes due 2036 and $750 million of 6.050% notes due 2056 in June 2026. Source

Quarterly results and net income

  • Revenue and EBITDA rose year on year: Revenues were $5.73 billion in the quarter, up 24% from $4.64 billion, and Consolidated Adjusted EBITDA was $1.80 billion, up 27%. Six-month revenues were $11.60 billion and EBITDA $4.14 billion, up 26%. Source
  • Net income swung on derivative values: Net income attributable to Cheniere was $3.07 billion for the quarter against $1.63 billion a year earlier, and a $0.43 billion loss for six months. Management tied the change mainly to fair value changes on IPM agreements. Source
  • Diluted EPS reported at $14.65: Net income per diluted share attributable to common stockholders was $14.65 for the quarter, against $7.30 a year earlier, and $(2.08) for six months. Diluted weighted average shares were 209.5 million. Source
  • Adjusted Net Income excludes derivative swings: Adjusted Net Income, a non-GAAP measure, was $632 million for the quarter against $498 million in 2025, and $1.64 billion for six months, excluding non-cash derivative fair value changes. Source

Cargo exports and volumes

  • Cargo exports rose 19% in quarter: 184 cargoes were exported in the quarter versus 154 a year earlier, and 371 in six months versus 322. Volumes were 672 TBtu for the quarter, up 22%, and 1,360 TBtu for six months, up 17%. Source
  • Commissioning and in-transit volumes: Commissioning activities accounted for 3 TBtu of quarterly exports and 9 TBtu for six months. 72 TBtu loaded in the period was in transit at June 30 and sold on a delivered basis. Source
  • Cumulative cargo count passes 4,940: As of July 31, 2026, the company reported over 4,940 cumulative LNG cargoes, totaling over 340 million tonnes, produced, loaded and exported from its liquefaction projects. Source

“Our strong financial and operational results year-to-date, coupled with our constructive outlook and enhanced visibility for the remainder of the year, have enabled us to once again raise”

Jack Fusco, Cheniere’s Chairman, President and Chief Executive Officer

Liquefaction projects and construction

  • Train 6 reached substantial completion: Midscale Train 6 of the CCL Stage 3 Project reached substantial completion in June 2026, after Train 5 in March. Trains 1-6 are now operational at CCL Stage 3. Source
  • CCL Stage 3 project 98.4% complete: CCL Stage 3 completion was 98.4% at June 30, with Train 7 under construction and commissioning. Engineering was 99.8% complete and construction 96.0% complete. Source
  • Midscale Trains 8 & 9 at 48.3%: CCL Midscale Trains 8 & 9 were 48.3% complete, with engineering at 91.5%, procurement at 69.9% and construction at 6.7%. Substantial completion is expected in 2H 2028. Source
  • FERC authorized about 5 mtpa more capacity: In June 2026 FERC authorized an increase of about 5 mtpa in aggregate production capacity for the previously authorized CCL Stage 3 and CCL Midscale Trains 8 & 9 projects. Source
  • Operating capacity about 55 mtpa: Approximately 55 mtpa of liquefaction capacity is in operation across Sabine Pass and Corpus Christi, with over 6 mtpa under construction and over 40 mtpa in regulatory permitting. Source

Margins, costs and tax items

  • Cost of sales moved with derivative gains: Cost of sales was $439 million in the quarter against $1,117 million a year earlier. It includes about $2.4 billion of derivative fair value gains in the quarter and $2.2 billion of losses for six months. Source
  • Operating costs down year on year: Operating and maintenance expense was $533 million in the quarter, against $559 million a year earlier. Selling, general and administrative expense was $88 million, against $99 million. Source
  • Higher margins per MMBtu on deliveries: Management said Consolidated Adjusted EBITDA rose on higher total margins on LNG delivered, mainly from higher volumes recognized in income, and on higher margins per MMBtu delivered. Source
  • Excise tax credit offset part of variance: Six-month results include a nonrecurring excise tax credit recognized in 2026, and lower income tax provisions than in 2025, which partly offset the derivative variance. Source

“We look forward to delivering full year financial results within these further improved ranges.”

Jack Fusco, Cheniere’s Chairman, President and Chief Executive Officer

Liquidity and debt financing

  • Liquidity stood at $7.48 billion: Total available liquidity at June 30 was $7.48 billion, made up of $1.10 billion of cash and cash equivalents and $5.96 billion of available credit facility commitments. Source
  • Revolving facilities extended and resized: The Cheniere revolver was extended one year and increased by $500 million to $1.75 billion. The CCH working capital facility was restated as the CCH Revolving Credit Facility, with maturity extended about four years and commitments cut to $1.0 billion. Source
  • Partnership notes issued, SPL notes redeemed: In June, Cheniere Partners issued $1.0 billion of 5.350% notes due 2036 and $750 million of 6.050% notes due 2056. Part of the proceeds fully redeemed $1.5 billion of SPL 5.00% notes due 2027. Source
  • Debt repayment and CCH commitments cancelled: Cheniere repaid about $253 million of consolidated long-term debt in the six months. In May, $600 million of unused CCH Credit Facility commitments were cancelled. Source

Dividends, buybacks and capital spending

  • Buybacks of $550 million in quarter: Cheniere repurchased about 2.2 million shares for $550 million in the quarter and 4.9 million shares for $1.1 billion in six months. Treasury shares were 71.7 million at June 30, against 66.8 million at year end. Source
  • Quarterly dividend of $0.555 per share: Dividends of $0.555 per share totaled about $116 million in the quarter and $233 million in the six months, paid at $1.110 per share for the half-year. Source
  • Growth capital invested with some equity: Growth capital investment was about $1.1 billion in the quarter, of which about $219 million was funded with equity. Six-month growth capital was $2.1 billion, with $520 million funded with equity. Source

Expansion projects and approvals

  • SPL Expansion first phase specified: The first phase of the SPL Expansion includes one train, Train 7, a boil-off gas re-liquefaction unit and supporting infrastructure, with expected capacity of over 6 mtpa including debottlenecking. Source
  • Overall SPL Expansion scale up to 20 mtpa: The SPL Expansion is expected to reach up to about 20 mtpa of peak capacity, to be executed in phases. Its FERC and DOE applications remain pending. Source
  • CCL Expansion regulatory filings pending: The CCL Expansion, up to about 24 mtpa of peak capacity, is also to be executed in phases. Its FERC application and DOE export application remain pending. Source

Coming up, as management said on 6 August 2026

  • Midscale Train 7 first LNG imminent: First LNG from Midscale Train 7 is expected imminently, with substantial completion expected in the fall of 2026. Source
  • Dividend payable August 18: The $0.555 per share dividend for the second quarter was declared in July and is payable on August 18, 2026. Source
  • SPL Expansion FID awaits approvals: A final investment decision on the SPL Expansion is subject to regulatory approvals and acceptable commercial and financing arrangements. FERC and DOE applications remain pending. Source

Risks management discussed

  • Regulatory: The DOE export authorization application for the SPL Expansion, for non-FTA countries, remains pending. Source
  • Financial: Management noted that net income includes derivative transaction impacts that cannot be determined at this time, so a run-rate net income forecast was not made. Source
  • Financial: Management said cash tax payments depend on commodity and market volatility and regulatory changes, which could affect the timing and amount of future cash taxes. Source

Earlier plans management reported on

  • Met: Train 6 substantial completion was reported as achieved in June; the prior release had expected Train 6 first LNG imminently. Source
  • Not stated: The release refers to substantial completions of Midscale Trains 1-4 that were announced earlier, in 2025. Source
  • Not stated: Management said it looks forward to delivering full-year results within the raised Consolidated Adjusted EBITDA and Distributable Cash Flow ranges. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.