Nuscale Power Corp.: Q3 FY2026 earnings call
What management said about Q3 FY2026, from the documents filed with the SEC on 5 November 2026: press release. The quarter’s numbers.
Key takeaways
- Net loss was $45.7 million: Net loss was $45.7 million, against $532.6 million a year earlier. Loss attributable to Class A stockholders was $43.7 million, or $(0.11) per share, against $(1.85). Source
- R&D rose on NPM component work: R&D expenses rose $7.0 million to $18.0 million, mainly from $6.7 million of added cost to advance the technological readiness and design maturity of NPM components. Source
- Doosan to fabricate reactor coolant system: NuScale signed an agreement with Doosan Enerbility to fabricate the upper reactor coolant system, which the release calls the most complex and foundational NPM component. Source
- ENTRA1 supports TVA program dialogue: NuScale said it continues to support its commercial partner ENTRA1 in its dialogue with the Tennessee Valley Authority on a program the release describes as the largest commercial nuclear deployment in U.S. history. Source
- Liquidity ended near $1.9 billion: Cash, cash equivalents and short- and long-term investments totaled $1.9 billion at September 30, 2026: cash $513.4 million, short-term investments $420.0 million and investments $930.7 million. Source
- Operating cash outflow widened in nine months: Net cash used in operating activities was $401.4 million for the nine months, against $255.9 million a year earlier. Accounts payable and accrued expenses accounted for a $261.2 million outflow. Source
“This was a significant quarter for NuScale as we progressed from development to physical production of our first commercial NuScale Power Module”
John Hopkins, NuScale President and Chief Executive Officer
What changed from last quarter
- New: New agreement with Doosan Enerbility to fabricate the upper reactor coolant system of the NPM, the first NPM component fabrication contract cited in this release. Source
- New: Nuclear-specific AI tools, developed with Nuclearn and NPX, deployed across engineering and knowledge-management functions. Source
- New: MillenniTEK fabricating first-of-a-kind reactor safety components for the NPMs, described as a second supply chain milestone. Source
Results for the quarter
- Revenue fell on prior-year FEED work: Revenue was $281 thousand against $8,242 thousand a year earlier. The company attributed the decline to Fluor FEED Phase 2 engineering work for the RoPower project, completed in late 2025, with no comparable 2026 activity. Source
- Net loss was $45.7 million: Net loss was $45.7 million, against $532.6 million a year earlier. Loss attributable to Class A stockholders was $43.7 million, or $(0.11) per share, against $(1.85). Source
- Operating loss fell to $64.8 million: Loss from operations was $64.8 million for the quarter, against $538.4 million a year earlier. The nine-month operating loss was $186.3 million, against $616.8 million. Source
Operating costs and investment income
- G&A down by $491.3 million: General and administrative expenses were $27.9 million, against $519.2 million a year earlier. The release gives no reason for the change. Source
- R&D rose on NPM component work: R&D expenses rose $7.0 million to $18.0 million, mainly from $6.7 million of added cost to advance the technological readiness and design maturity of NPM components. Source
- Other expenses rose on project staffing: Other expenses rose $8.1 million to $19.0 million. Management attributed this to engineers and project staff working on fewer commercial projects, lowering the allocation to cost of sales, and to higher compensation as supply chain resources were added. Source
- Investment income rose $13.4 million: Investment income was $19.1 million, against $5.8 million a year earlier. Management cited a stronger cash position, higher interest rates and greater investments in cash equivalents, short-term investments and long-term investments. Source
“Our contract with Doosan Enerbility to fabricate the upper reactor coolant system of the NPM moves our Nuclear Regulatory Commission-approved design into actual build and sets the foundation for all modules to follow.”
John Hopkins, NuScale President and Chief Executive Officer
Supply chain and partner dialogue
- Doosan to fabricate reactor coolant system: NuScale signed an agreement with Doosan Enerbility to fabricate the upper reactor coolant system, which the release calls the most complex and foundational NPM component. Source
- AI tools deployed in engineering: Nuclear-specific AI tools, developed with Nuclearn and NPX, were deployed across engineering and knowledge-management functions, counted as one of two supply chain maturity milestones. Source
- MillenniTEK fabricating reactor safety parts: Together with MillenniTEK, NuScale is fabricating first-of-a-kind reactor safety components for the NPMs, counted as the second of two supply chain milestones. Source
- ENTRA1 supports TVA program dialogue: NuScale said it continues to support its commercial partner ENTRA1 in its dialogue with the Tennessee Valley Authority on a program the release describes as the largest commercial nuclear deployment in U.S. history. Source
Liquidity and cash flow
- Liquidity ended near $1.9 billion: Cash, cash equivalents and short- and long-term investments totaled $1.9 billion at September 30, 2026: cash $513.4 million, short-term investments $420.0 million and investments $930.7 million. Source
- Operating cash outflow widened in nine months: Net cash used in operating activities was $401.4 million for the nine months, against $255.9 million a year earlier. Accounts payable and accrued expenses accounted for a $261.2 million outflow. Source
- Common stock issuance funded the period: Net proceeds from common stock issuance were $984.5 million for the nine months, against $562.4 million a year earlier. The six-month release showed the same $984.5 million. Source
- Investing outflows reached $902.4 million: Net cash used in investing activities was $902.4 million for nine months, including $975.1 million of investment purchases and $747.6 million of short-term investment purchases. Capital expenditure was $2.0 million. Source
Balance sheet and share count
- Accounts payable fell from year-end: Accounts payable and accrued expenses were $26.7 million at September 30, 2026, against $286.5 million at December 31, 2025. Source
- Total equity reached $1.97 billion: Total stockholders' equity was $1,974.4 million, with noncontrolling interests at a deficit of $49.7 million. Total assets were $2,020.0 million and total liabilities were $45.6 million. Source
- Class A shares outstanding rose: Class A shares outstanding were 410,541,392 at September 30, 2026, against 318,480,601 at December 31, 2025. Class B shares outstanding were 19,332,018. Source
- Paid-in capital rose, deficit grew: Additional paid-in capital was $2,892.1 million, against $1,901.7 million at year-end. The accumulated deficit was $868.1 million, against $732.9 million. Source
Management view and production path
- Quarter described as move to production: The CEO described the quarter as the company's progression from development to physical production of its first commercial NuScale Power Module. Source
- Supply chain deepening cited with cash: The CEO said the company continued to deepen its global supply chain and ended the period with liquidity that gives flexibility for strategic investments. Source
- Doosan contract sets module foundation: The CEO said the Doosan contract moves the Nuclear Regulatory Commission-approved design into actual build and sets the foundation for all modules to follow. Source
Coming up, as management said on 5 November 2026
- Investments toward full-scale production: Management said its liquidity gives flexibility for strategic investments needed to move toward full-scale production. The release gives no amounts, timing or milestones. Source
Other quarters
Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.