Nuscale Power Corp.: Q2 FY2026 earnings call

What management said about Q2 FY2026, from the documents filed with the SEC on 5 August 2026: press release. The quarter’s numbers.

Key takeaways

  • TVA discussions toward definitive agreement: ENTRA1, NuScale's exclusive global strategic partner, continues discussions with TVA toward a definitive power purchase agreement for what the release calls potentially the largest nuclear deployment program in U.S. history. Source
  • RoPower conditions on Romanian vote: NuScale is working with Nuclearelectrica and RoPower Nuclear to meet conditions tied to the Nuclearelectrica shareholder vote. The vote concerns a project to deploy six NPMs at a former coal plant site in Doicești, Romania. Source
  • Paragon awarded HIPS design contract: NuScale awarded Paragon, a supplier of safety-related products, a contract to complete final design development of the Highly Integrated Protection System, which the release calls a supply chain readiness milestone. Source
  • Cash and investments reached $1.9 billion: Cash, cash equivalents and short- and long-term investments were $1.9 billion at June 30, 2026, against $1.0 billion at March 31, 2026, per the first-quarter release. Source
  • Share sales raised $984 million: Proceeds from issuing common stock, net of fees, were $984,475 thousand in the six months, against $37,261 thousand in the first quarter. Class A shares outstanding reached 410,367,790 at June 30. Source
  • Revenue fell to $75 thousand: Revenue was $75 thousand for the quarter, down $8.0 million. The release attributes this to FEED Phase 2 work for RoPower, completed in late 2025, with no comparable 2026 activity. Source
  • Other expenses rose $8.0 million: Other expenses rose $8.0 million to $18,547 thousand. The release attributes this mainly to engineers and project personnel working on fewer commercial projects, lowering the cost of sales allocation. Source

“As demand for clean, reliable power grows more urgent by the day, the question for off- takers is no longer whether to go with nuclear - it is which technology can actually deliver, and when,”

John Hopkins, NuScale President and Chief Executive Officer

What changed from last quarter

  • New: Paragon was awarded a contract for final design development of the Highly Integrated Protection System. The first-quarter release does not mention this award. Source
  • New: The TVA item moved from planning progress in the first quarter to discussions toward a definitive power purchase agreement in the second. Source

Customer projects and pipeline

  • TVA discussions toward definitive agreement: ENTRA1, NuScale's exclusive global strategic partner, continues discussions with TVA toward a definitive power purchase agreement for what the release calls potentially the largest nuclear deployment program in U.S. history. Source
  • RoPower conditions on Romanian vote: NuScale is working with Nuclearelectrica and RoPower Nuclear to meet conditions tied to the Nuclearelectrica shareholder vote. The vote concerns a project to deploy six NPMs at a former coal plant site in Doicești, Romania. Source
  • First-quarter TVA capacity framing: The first-quarter release described the TVA program as up to 6 gigawatts of NuScale SMR capacity. The second-quarter release gives no capacity figure for the program.

Supply chain and product readiness

  • Paragon awarded HIPS design contract: NuScale awarded Paragon, a supplier of safety-related products, a contract to complete final design development of the Highly Integrated Protection System, which the release calls a supply chain readiness milestone. Source
  • R&D rose on module readiness work: R&D rose $6.6 million to $18,429 thousand. The release cites $7.1 million of higher costs to advance the technological readiness and design maturity of NPM components, partly offset by $0.6 million lower regulatory costs. Source
  • Module output and configuration described: The release says each NuScale Power Module generates 77 MWe, with configurations scalable up to 924 MWe across 12 modules. Source

“At NuScale, we have spent years doing the work that makes near-term deployment possible, and that work is now substantially complete.”

John Hopkins, NuScale President and Chief Executive Officer

Liquidity, cash and capital

  • Cash and investments reached $1.9 billion: Cash, cash equivalents and short- and long-term investments were $1.9 billion at June 30, 2026, against $1.0 billion at March 31, 2026, per the first-quarter release. Source
  • Share sales raised $984 million: Proceeds from issuing common stock, net of fees, were $984,475 thousand in the six months, against $37,261 thousand in the first quarter. Class A shares outstanding reached 410,367,790 at June 30. Source
  • Operating cash used rose to $373 million: Net cash used in operating activities was $372,860 thousand for the six months, against $56,107 thousand a year earlier. The release shows a $268,201 thousand outflow in accounts payable and accrued expenses. Source
  • Equity rose to $2.0 billion: Total stockholders' equity was $2,013,657 thousand at June 30, 2026, against $1,113,551 thousand at December 31, 2025. Source
  • Equipment purchases of $2.0 million: Purchases of property, plant and equipment were $1,953 thousand for the six months. The statement shows no amount for the prior-year period. Source

Revenue and gross margin

  • Revenue fell to $75 thousand: Revenue was $75 thousand for the quarter, down $8.0 million. The release attributes this to FEED Phase 2 work for RoPower, completed in late 2025, with no comparable 2026 activity. Source
  • Six-month revenue fell to $640 thousand: Six-month revenue was $640 thousand, against $21,429 thousand a year earlier, of which $14,700 thousand was from a related party. Source
  • Gross margin was $(152) thousand: Gross margin was $(152) thousand for the quarter, against $1,781 thousand a year earlier. Cost of sales was $(227) thousand, against $(6,273) thousand. Source
  • Loss per share held at $0.13: Net loss attributable to Class A stockholders was $(47,539) thousand, against $(17,641) thousand. Basic and diluted loss per share was $(0.13) in both periods. Source

“No one is better positioned to deliver carbon-free, 24/7 power on the shortest possible timeline.”

John Hopkins, NuScale President and Chief Executive Officer

Overhead and investment income

  • G&A rose on organizational costs: G&A rose $4.4 million to $26,875 thousand, mainly on $3.9 million of higher organizational costs, according to the release. Source
  • Other expenses rose $8.0 million: Other expenses rose $8.0 million to $18,547 thousand. The release attributes this mainly to engineers and project personnel working on fewer commercial projects, lowering the cost of sales allocation. Source
  • Investment income rose $8.5 million: Investment income rose $8.5 million to $13,940 thousand, which the release attributes to a stronger cash position and higher investments in cash equivalents and short- and long-term investments. Source
  • Pre-tax loss rose to $50.1 million: Loss from operations was $(64,003) thousand against $(43,082) thousand. Loss before income taxes was $(50,063) thousand against $(37,609) thousand. Source

Headcount, compensation and filer costs

  • Headcount growth lifted personnel costs: The release ties $1.2 million of higher personnel and equity-based compensation costs to increased headcount, within the G&A increase. Source
  • Supply chain resources drove compensation: Other compensation rose as the company ramped up resources supporting supply chain readiness and delivery of future commercial projects. Source
  • Large accelerated filer legal costs fell: Legal fees fell $1.0 million now that the initial costs of becoming a large accelerated filer have passed, according to the release. Source

Figures management reported

FigureReported
Supply chain partners and agreements Sourcemore than 60 partners; over 30 agreements executed
RoPower planned NuScale Power Modules Sourcesix

Risks management discussed

  • Demand: The TVA project depends on a definitive power purchase agreement that the release describes as still under discussion. Source
  • External: Progress on RoPower depends on meeting conditions attached to the Nuclearelectrica shareholder vote, which the release describes as still being addressed. Source

Earlier plans management reported on

  • Not stated: In the first quarter, Nuclearelectrica shareholders approved proceeding with the next RoPower phase. The second-quarter release describes conditions still being addressed.
  • Not stated: The first-quarter release said work with TVA continued to progress planning for the program.

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.