Riot Platforms, Inc.: Q3 FY2026 earnings call

What management said about Q3 FY2026, from the documents filed with the SEC on 4 November 2026: press release. Guidance figures: 8 new. The quarter’s numbers.

Key takeaways

  • Revenue rose 1% year on year: Total revenue was $181.4 million against $180.2 million a year earlier, a 1% increase. Source
  • Data Center revenue from leases and fit-out: Data Center revenue was $18.4 million, including $7.7 million base rent, $0.5 million variable lease revenue and $10.2 million tenant fit-out reimbursement. Source
  • Engineering revenue more than doubled: Engineering revenue was $47.0 million against $19.1 million, driven by third-party data center demand for custom electrical equipment. Source
  • 1,151 MW of capacity contracted: Together with the AMD contract and the Rockdale lease with the same Frontier AI Lab, Riot has contracted 1,151 MW of critical IT capacity. Source
  • Rent payable on full capacity: Rent is payable on the full 910 MW of Corsicana capacity regardless of how much of it is used. Source
  • Cost to mine fell to $39,265: Cost to mine one bitcoin excluding depreciation was $39,265 against $46,324, and 55.4% of production value against 40.5%, on lower power costs and higher production. Source
  • Cash and bitcoin of $950.2 million: Cash and bitcoin totalled $950.2 million at quarter end, including $748.2 million of cash, of which $79.2 million is restricted, and 2,418 bitcoin worth about $202.0 million. Source
  • Bitcoin sold to fund data centers: Riot sold 20,264 bitcoin in the first nine months for about $1.5 billion, primarily to fund data center development. Source

“the largest lease in Riot’s history: a 15-year triple-net powered land lease with a leading Frontier AI Lab for the entirety of our Corsicana campus”

Jason Les, CEO of Riot

Guidance

AreaPeriodFigureAgainst last quarter
Corsicana delivery schedule SourceSeptember 2027 to July 2028400 MW in September 2027, 200 MW in January 2028 and 310 MW in July 2028New
Contract value and rent Sourceinitial 15-year termapproximately $28 billion total contract value; approximately $1.8 billion average annual rentNew
Extension options Sourceif both five-year extension options are exercisedapproximately $54 billionNew
Capital cost SourceCorsicana development$6 million per IT MW, or $5.5 billion overallNew
Riot-funded share of capital SourceCorsicana development$2 million per IT MW for site work and electrical infrastructureNew
Unlevered yield on cost Sourceinitial termapproximately 33%New
Net operating income, Corsicana Sourceinitial term; average annualapproximately $1.8 billion; NOI margin approximately 99%New
Net operating income, all contracted capacity Sourceat full deploymentmore than $2 billion of average annual net operating incomeNew

What changed from last quarter

  • New: Riot executed a 15-year triple-net powered land lease for the entire Corsicana campus with a leading Frontier AI Lab. Source
  • New guidance: Corsicana delivery schedule and capital and NOI figures appear for the first time; the prior release gave a Rockdale delivery schedule. Source
  • New: Management said it does not currently anticipate issuing equity to fund announced projects. Source
  • Ended: Riot repaid and terminated its $200 million Coinbase credit facility and released all pledged bitcoin. Source

Results and growth drivers

  • Revenue rose 1% year on year: Total revenue was $181.4 million against $180.2 million a year earlier, a 1% increase. Source
  • Bitcoin production rose 16%: Riot produced 1,637 bitcoin against 1,406 a year earlier, a 16% increase in production. Source
  • Data Center and Engineering offset mining: Growth in Data Center and Engineering revenue offset lower Bitcoin Mining revenue in the quarter. Source

Segments and revenue lines

  • Data Center revenue from leases and fit-out: Data Center revenue was $18.4 million, including $7.7 million base rent, $0.5 million variable lease revenue and $10.2 million tenant fit-out reimbursement. Source
  • Engineering revenue more than doubled: Engineering revenue was $47.0 million against $19.1 million, driven by third-party data center demand for custom electrical equipment. Source
  • Bitcoin Mining revenue declined: Bitcoin Mining revenue was $116.0 million against $160.8 million, mainly on a lower average bitcoin price of $70,855 against $114,361. Source

“As these significant contracted cash flows come online, we will allocate our capital with discipline to whichever use creates the most value per share”

Jason Les, CEO of Riot

Contracted capacity and Corsicana lease

  • 1,151 MW of capacity contracted: Together with the AMD contract and the Rockdale lease with the same Frontier AI Lab, Riot has contracted 1,151 MW of critical IT capacity. Source
  • Tenant runs compute and pays power: The tenant buys, installs, owns and operates the modular compute on the powered pads and bears substantially all operating costs, with power as a pass-through. Source
  • Rent payable on full capacity: Rent is payable on the full 910 MW of Corsicana capacity regardless of how much of it is used. Source
  • Riot delivers land and power: Riot delivers the land, power infrastructure and powered pads on a contiguous 332-acre parcel, and keeps the high- and medium-voltage infrastructure. Source
  • Corsicana needs half a Tier 3 build's capital: Management said the Corsicana development needs about half the capital of a Tier 3 build, limiting procurement and operating risk to Riot. Source
  • Lease positions Riot as developer: Management said the two contracted projects establish Riot as a leading developer of large-scale digital infrastructure. Source

Mining costs and margins

  • Cost to mine fell to $39,265: Cost to mine one bitcoin excluding depreciation was $39,265 against $46,324, and 55.4% of production value against 40.5%, on lower power costs and higher production. Source
  • Curtailment credits lowered unit cost: Power curtailment credits of $24.7 million equalled $15,067 per bitcoin mined and sit outside cost of revenue. Source
  • Depreciation raises full cost per bitcoin: With miner depreciation included, cost was $78,805 per bitcoin, 111.2% of production value, against $89,074 and 77.9% a year earlier. Source

Cash, bitcoin and liquidity

  • Cash and bitcoin of $950.2 million: Cash and bitcoin totalled $950.2 million at quarter end, including $748.2 million of cash, of which $79.2 million is restricted, and 2,418 bitcoin worth about $202.0 million. Source
  • Bitcoin sold to fund data centers: Riot sold 20,264 bitcoin in the first nine months for about $1.5 billion, primarily to fund data center development. Source
  • Corsicana cash from existing liquidity: Riot's cash contribution to the Corsicana development is expected to come from existing liquidity. Source

Depreciation and Adjusted EBITDA

  • Future miner depreciation schedule: Future depreciation on the existing miner fleet totals $419,267, with $223,713 scheduled for 2027 and $67,749 for the rest of 2026. Source
  • Depreciation and impairment rose: Total depreciation and amortization was $123,921 in the quarter against $82,929 a year earlier; impairment of property and equipment was $18,453. Source
  • Adjusted EBITDA excludes non-cash items: Adjusted EBITDA was $191,333 against $197,197 a year earlier, after adding back stock-based compensation and derivative fair value changes. Source

Coming up, as management said on 4 November 2026

  • Reimbursement financing expected: Management expects reimbursements to the tenant to be funded with non-recourse project debt sized to contracted rent. Source

Figures management reported

FigureReported
Critical IT capacity leased, cumulative Source1,151 MW
Corsicana critical IT capacity leased Source910 MW
Bitcoin produced in the quarter Source1,637
Bitcoin held at quarter end Source2,418

Risks management discussed

  • Operational: Management said the lease structure significantly limits Riot's procurement, development and ongoing operational risk. Source
  • Financial: If comparable financing is unavailable, the tenant would fund the reimbursements directly and recover them as a credit against rent. Source

Earlier plans management reported on

  • Not stated: The release refers to the 25 MW delivered to AMD as stabilized and does not state its status against the original plan. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.