Riot Platforms, Inc.: Q2 FY2026 earnings call

What management said about Q2 FY2026, from the documents filed with the SEC on 10 August 2026: press release. Guidance figures: 6 new. The quarter’s numbers.

Key takeaways

  • Revenue rose 14% year-over-year: Total revenue was $174.2 million, up 14% from $153.0 million in the same quarter of 2025. Source
  • Data Center segment revenue reported: Data Center revenue was $23.2 million: $4.9 million operating lease revenue and $18.3 million tenant fit-out services revenue. The company called this its second quarter of Data Center segment revenue. Source
  • Bitcoin Mining revenue declined: Bitcoin Mining revenue was $113.7 million, down from $140.9 million. The company attributed the decline to lower average bitcoin prices and higher global network hash rate, partly offset by higher Riot hash rate. Source
  • 191 MW Rockdale lease signed: The company executed a 20-year lease for 191 MW of critical IT capacity at Rockdale with a frontier AI lab, expected to generate about $9.1 billion of initial contract revenue. Source
  • Cost to mine rose year-over-year: Cost to mine one bitcoin, excluding depreciation, was $49,912, against $48,992 in the same quarter of 2025. Source
  • 241 MW contracted across two tenants: With the AMD lease, the company has contracted 241 MW of critical IT capacity with two companies in the AI ecosystem. Source
  • Over $1.2 billion liquid assets: Liquid assets exceeded $1.2 billion at quarter end, including 11,380 bitcoin, of which 5,821 were held as collateral, valued at about $666.0 million. Source

“Today's announcement of a landmark 20-year, 191-megawatt data center lease with a leading frontier AI lab marks a defining moment in our evolution into a leading developer of large-scale data centers”

Jason Les, CEO of Riot

Guidance

AreaPeriodFigureAgainst last quarter
Rockdale lease contract revenue Sourceinitial 20-year term through June 2048$9.1 billionNew
Rockdale lease contract value with extensions Sourcetwo five-year extension options$16.1 billionNew
Rockdale lease net operating income Sourcebase lease term$7.3 to $8.2 billion cumulative; $365 to $411 million average annualNew
Rockdale lease delivery SourceDecember 2027initial 96 IT MWNew
Rockdale lease delivery SourceJune 2028full 191 IT MWNew
AMD expansion Phase 3 and Phase 4 delivery SourceNovember 2026 (Phase 3); May 2027 (Phase 4)10 MW Phase 3; 15 MW Phase 4; AMD total 50 MW fully deployedNew

What changed from last quarter

  • New: After quarter end, the company executed a 20-year Data Center Lease for 191 MW of critical IT capacity at Rockdale with a frontier AI lab. Source
  • New guidance: Delivery schedule given for the Rockdale lease: initial 96 IT MW in December 2027, full 191 IT MW by June 2028. Source
  • New guidance: Net operating income estimate given for the Rockdale lease over its base term. Source

Results and growth drivers

  • Revenue rose 14% year-over-year: Total revenue was $174.2 million, up 14% from $153.0 million in the same quarter of 2025. Source
  • Net loss and Adjusted EBITDA reported: The company reported a net loss of $237.2 million, against net income of $219.5 million a year earlier, and Adjusted EBITDA of negative $69.7 million. Source
  • Bitcoin output rose year-over-year: The company produced 1,587 bitcoin in the quarter, up from 1,426 in the same quarter of 2025. Source

Segments and revenue mix

  • Data Center segment revenue reported: Data Center revenue was $23.2 million: $4.9 million operating lease revenue and $18.3 million tenant fit-out services revenue. The company called this its second quarter of Data Center segment revenue. Source
  • Bitcoin Mining revenue declined: Bitcoin Mining revenue was $113.7 million, down from $140.9 million. The company attributed the decline to lower average bitcoin prices and higher global network hash rate, partly offset by higher Riot hash rate. Source
  • Engineering revenue rose: Engineering revenue was $37.3 million, compared with $10.6 million in the same quarter of 2025. Source

“Our platform stands apart through three elements working together: multi-gigawatt-scale power capacity that is already fully approved and energized, in-house data center development expertise, and the ability to engineer custom infrastructure for computing's most demanding workloads.”

Jason Les, CEO of Riot

Customers and data center leases

  • 191 MW Rockdale lease signed: The company executed a 20-year lease for 191 MW of critical IT capacity at Rockdale with a frontier AI lab, expected to generate about $9.1 billion of initial contract revenue. Source
  • Extension options raise total value: The lease includes two five-year extension options at the tenant's election, with total potential contract value of about $16.1 billion if both are exercised. Source
  • Estimated NOI from the lease: Estimated cumulative NOI over the base term is $7.3 to $8.2 billion, or $365 to $411 million a year on average. Source

Mining costs and output

  • Cost to mine rose year-over-year: Cost to mine one bitcoin, excluding depreciation, was $49,912, against $48,992 in the same quarter of 2025. Source
  • Power costs and Kentucky expansion cited: The company said the increase in cost to mine was primarily driven by higher power costs and the expansion at its Kentucky facilities. Source
  • Miners paid from cash balance: Cash paid for miner purchases was $25.2 million in the quarter, against $71.3 million a year earlier, paid from the company's cash balance. Source

“Riot’s in-house procurement, engineering and construction capabilities continue to underpin this delivery record.”

Riot Platforms, Inc., press release

Contracted backlog and demand

  • 241 MW contracted across two tenants: With the AMD lease, the company has contracted 241 MW of critical IT capacity with two companies in the AI ecosystem. Source
  • About $9.8 billion of contracted revenue: The company put long-term contracted revenue from its leases at about $9.8 billion, with the leases executed in just over six months. Source
  • Second tenant secured at Rockdale: The company said the transaction secures a second tenant at Rockdale, following the January 16, 2026 AMD lease announcement. Source

Build-out and delivery schedule

  • AMD expansion construction underway: Construction is underway on the 25 MW AMD expansion, following completion of the initial 25 MW. Source
  • Phase 3 and Phase 4 dates set: AMD Phase 3 (10 MW) is due November 2026 and Phase 4 (15 MW) May 2027, when AMD's 50 MW total is fully deployed. Source
  • Rockdale phased delivery timetable: The 191 MW Rockdale lease is set for phased delivery, with 96 IT MW in December 2027 and the full 191 IT MW by June 2028. Source

Liquidity and financing

  • Over $1.2 billion liquid assets: Liquid assets exceeded $1.2 billion at quarter end, including 11,380 bitcoin, of which 5,821 were held as collateral, valued at about $666.0 million. Source
  • Cash and restricted amount: Cash was $548.9 million at quarter end, of which $77.5 million is restricted. Source
  • $573 million interim facility from Morgan Stanley: Morgan Stanley provided a $573 million interim financing facility to fund initial development costs while the credit backstop is finalized. Source

Platform and strategy

  • Vision of a trusted digital platform: The company's stated vision is to be the world's most trusted platform for powering and building the next digital world. Source
  • Expansion into data center development: The prior-quarter release said the company is now expanding into data center development, building a foundational position in the digital economy.
  • Mining and engineering sites: The company runs bitcoin mining and digital infrastructure in central Texas and Kentucky, with engineering and fabrication in Denver and Houston. Source

Coming up, as management said on 10 August 2026

  • Rockdale phased delivery: Initial 96 IT MW expected in December 2027, with full 191 IT MW deployment expected by June 2028. Source
  • Financing backstop being finalized: The interim facility funds initial development while the investment-grade credit backstop is finalized. Source
  • AMD fully deployed May 2027: AMD's total contracted 50 MW is expected to be fully deployed when Phase 4 is delivered in May 2027. Source

Figures management reported

FigureReported
Bitcoin produced Source1,587
Contracted critical IT capacity Source241 MW
Rockdale lease capacity Source191 MW
AMD contracted capacity50 MW
Cost to mine one bitcoin, excluding depreciation Source$49,912

Risks management discussed

  • External: Lower average bitcoin prices and higher global network hash rate reduced Bitcoin Mining revenue. Source
  • Operational: Higher power costs were cited as a driver of the increase in cost to mine bitcoin. Source
  • Financial: The initial development of the Rockdale lease is funded by an interim facility while the investment-grade credit backstop is finalized. Source

Earlier plans management reported on

  • Met: The company said delivery of the initial 25 critical IT MW to AMD was completed on time and on budget. Source
  • On track: The company said the 10 MW Phase 3 is on track for delivery in November 2026. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.