What management said about Q3 FY2026, from the documents filed with the SEC on 16 November 2026: press release. Guidance figures: 2 new, 1 kept. The quarter’s numbers.

Key takeaways

  • Restructuring completed September 11: The company completed its restructuring and recapitalization under the UK Restructuring Plan on Sept. 11, 2026. Source
  • Debt principal cut to $0.7 billion: Debt principal on the CoreCo term loans fell from about $5.7 billion to about $0.7 billion; total balance-sheet debt also includes FLNG 2 non-recourse loans. Source
  • Revenue rose $109.7 million sequentially: Total revenues were $335.8 million, up $109.7 million from the second quarter of 2026, mainly from cargo sales, contract novation revenue and Mexico volumes. Source
  • Adjusted EBITDA reached $48.4 million: Adjusted EBITDA was $48.4 million for the quarter, with higher cargo sales margin and novation revenue, partly offset by higher operating, maintenance and turbine lease costs. Source
  • Non-cash impairments of $467.9 million: The company recorded $467.9 million of non-cash asset impairments, $160.8 million of interest expense and $47.3 million of transaction and integration costs tied to the restructuring. Source
  • FLNG 1 offline after turbine fault: FLNG 1 is offline after a mechanical issue with the turbine that powers its compressor; the liquefaction equipment itself was not affected. Source
  • Further liquidity actions under review: Beyond returning FLNG 1 to service, the company continues to evaluate other actions to improve its liquidity and cash flows. Source

“With our restructuring complete, we are now a transformed company with significantly reduced debt and a simplified, capital-light business plan.”

Wes Edens, Chief Executive Officer of NFE

Guidance

AreaPeriodFigureAgainst last quarter
FLNG 1 return to service Sourcefourth quarter of 2026fourth quarter of 2026Kept
FLNG 1 turbine readiness SourceNovember 2026November 23rdNew
Turbine lease deliveries Sourcefourth quarter of 2026 to first quarter of 2027fourth quarter of 2026 to first quarter of 2027New

What changed from last quarter

  • New: The restructuring under the UK Restructuring Plan was completed, with creditors receiving the Brazil business and equity. Source
  • Ended: The Brazil business was disposed of and is now presented as discontinued operations. Source
  • New: NFE effected a 1-for-50 reverse stock split of its Class A common stock. Source
  • New: In October 2026 NFE agreed to lease ten mobile turbines, up to 300 MW, for an initial five-year term. Source
  • New: Beginning in Q3 2026, Adjusted EBITDA excludes discontinued operations and the restructuring and extinguishment gains. Source

Restructuring and capital structure

  • Restructuring completed September 11: The company completed its restructuring and recapitalization under the UK Restructuring Plan on Sept. 11, 2026. Source
  • Debt principal cut to $0.7 billion: Debt principal on the CoreCo term loans fell from about $5.7 billion to about $0.7 billion; total balance-sheet debt also includes FLNG 2 non-recourse loans. Source
  • Creditors received Brazil and preferred equity: Creditors received the Brazil business, Class A common stock, and preferred stock and interests with liquidation preferences of $2.45 billion and $0.2 billion. Source

Results and growth drivers

  • Revenue rose $109.7 million sequentially: Total revenues were $335.8 million, up $109.7 million from the second quarter of 2026, mainly from cargo sales, contract novation revenue and Mexico volumes. Source
  • Net income driven by non-cash gains: Net income was $863.4 million, driven by $1.6 billion of non-cash gains on the restructuring and extinguishment of debt. Source
  • Adjusted EBITDA reached $48.4 million: Adjusted EBITDA was $48.4 million for the quarter, with higher cargo sales margin and novation revenue, partly offset by higher operating, maintenance and turbine lease costs. Source
  • Diluted EPS from continuing operations: Diluted EPS from continuing operations was $4.70, against a loss per share of $(50.51) in the third quarter of 2025. Source
  • Nine-month net income positive: Nine-month net income was $89.8 million, against a net loss of $984.9 million a year earlier. Source

“Our power assets are in great demand and the worldwide need for LNG continues to be robust.”

Wes Edens, Chief Executive Officer of NFE

Costs, impairments and transaction costs

  • Non-cash impairments of $467.9 million: The company recorded $467.9 million of non-cash asset impairments, $160.8 million of interest expense and $47.3 million of transaction and integration costs tied to the restructuring. Source
  • Operations and overhead costs rose: Operations and maintenance was $73.1 million, up from $55.5 million, and SG&A was $65.5 million, up from $53.7 million. Source
  • Operating loss from continuing operations: Operating loss from continuing operations was $492.4 million, against $96.7 million a year earlier. Source

FLNG 1 outage and liquidity actions

  • FLNG 1 offline after turbine fault: FLNG 1 is offline after a mechanical issue with the turbine that powers its compressor; the liquefaction equipment itself was not affected. Source
  • Uptime before the outage: Before the outage, FLNG 1 was online about 98% of the time in 2026, excluding scheduled maintenance. Source
  • Further liquidity actions under review: Beyond returning FLNG 1 to service, the company continues to evaluate other actions to improve its liquidity and cash flows. Source

Contracts, shipping and discontinued Brazil

  • Operating revenue up, charter revenue down: Operating revenue was $255.9 million, up from $146.4 million, while vessel charter revenue was $15.8 million, down from $61.0 million. Source
  • Other revenue lower: Other revenue was $24.7 million, down from $29.0 million a year earlier. Source
  • Brazil loss shown as discontinued: Brazil results are shown as discontinued operations, with a net loss of $27.7 million in the quarter and $130.5 million for nine months. Source

Cash flow, debt and balance sheet

  • Operating cash outflow for nine months: Net cash used in operating activities was $270.1 million for the nine months, against $507.2 million a year earlier. Source
  • Capital expenditures lower year on year: Capital expenditures were $185.1 million for the nine months, against $592.2 million a year earlier. Source
  • Cash and debt at quarter end: Cash and cash equivalents were $270.5 million at Sept. 30, 2026; current debt was $43.4 million and long-term debt $1,422.8 million. Source
  • Total liabilities down sharply: Total liabilities were $2,823.7 million, down from $10,246.0 million at Dec. 31, 2025; mezzanine equity was $2,658.8 million. Source

Share data and reporting basis

  • Income to common stockholders: Net income attributable to common stockholders was $11.9 million, against a loss of $269.6 million a year earlier. Source
  • Weighted share count: Basic weighted average shares were 7.9 million and diluted 10.4 million in the third quarter, against 5.6 million a year earlier. Source
  • Discontinued operations diluted EPS: Discontinued operations contributed diluted EPS of $(2.65) in the quarter, against $2.56 a year earlier. Source

Coming up, as management said on 16 November 2026

  • Testing after turbine arrives: After the turbine is ready, testing and installation are expected to take several weeks before FLNG 1 returns. Source

Risks management discussed

  • Operational: FLNG 1 return timing depends on turbine repair, which management says is outside the company's control. Source
  • Financial: Management disclosed substantial doubt about the company's ability to continue as a going concern. Source

Earlier plans management reported on

  • Not stated: Management continues to expect FLNG 1 to return to service in Q4 2026, after the turbine outage. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.