  • Net loss and EPS in quarter: The company reported revenues of $470.5 million, a net loss of $197.4 million, diluted EPS of $(0.73) and Adjusted EBITDA of $82.3 million. Revenues were $679.0 million in the fourth quarter of 2024 and $690.3 million in the first quarter of 2024.
  • Terminals margin fell on novation: Terminals and Infrastructure segment operating margin was $74.6 million, against $206.1 million in the fourth quarter of 2024. The fourth quarter included $235.6 million of novation income, which did not recur. Source
  • Interest expense rose sharply: Interest expense was $213.7 million, up $114.2 million from the fourth quarter of 2024. Less interest was capitalized, $74.1 million compared with $139.5 million, as the Fast LNG project and Santa Catarina facility entered service. Source
  • Investing outflow funded by borrowing: Investing cash outflow was $335.9 million, including $340.5 million of capital expenditures. Total borrowings were $943.6 million, used mainly for the onshore FLNG project and corporate expenses. Source
  • Liquidity judged insufficient in full: Under the going-concern assessment, management concluded that current liquidity and forecast operating cash flows are not sufficient in full to meet obligations as they become due, excluding planned asset sales. Source
  • First Fast LNG unit fully commissioned: The first Fast LNG unit has been fully commissioned. Management is increasing available liquefaction capacity through optimization projects. Source
  • PREPA claim for $659 million: The company is pursuing a $659 million request for equitable adjustment tied to early termination of its emergency power contract with PREPA. The amount and timing of any recovery are uncertain. Source

“The closing of the sale of our Jamaican assets to Excelerate is a significant milestone for the Company as we streamline our operations and paydown corporate debt through asset sales,”

Wes Edens, Chairman and CEO of New Fortress Energy

Guidance

AreaPeriodFigureAgainst last quarter
Capital expenditures Sourceremaining committed, as of March 31, 2025approximately $881 million
Fast LNG unit cost Sourcefully completed units, on average$1.0 billion to $2.0 billion per unit
LNG production Sourceannually from the first Fast LNG facilityup to 70 TBtu
Power plant completion Source20252025
Power plant completion Source20262026
Debt principal payments Sourcequarterly, beginning June 2025approximately $3.2 million per quarter
Financial covenant Sourcefiscal quarters ending September 30, 2025 through December 31, 20266.75 to 1.00 (Sep 30, 2025); 6.50 to 1.00 (Dec 31, 2025); 7.25 to 1.00 (Mar 31 and Sep 30, 2026); 6.75 to 1.00 (Dec 31, 2026 and after)
LNG use Sourceper day, Puerto Sandino power plantapproximately 57,000 MMBtu per day
Clean hydrogen production Sourceper day at ZeroPark Iup to 86,000 kg per day (approximately 31,000 TPA)

What changed from last quarter

  • Ended: The Jamaica Business was sold to Excelerate Energy. Net proceeds were about $678 million from a $1.055 billion price, with $99 million held in escrow. Montego Bay and Old Harbour results stop being reported from the second quarter of 2025. Source
  • New: Credit agreement amendments provide a covenant holiday for the first lien debt ratio and fixed charge coverage ratio for the quarter ending June 30, 2025. Source
  • New: A consolidated subsidiary agreed to issue up to $350.0 million of 15.0% senior secured notes due 2029, with interest payable in kind for the first 30 months. Source
  • New: Lenders agreed to incremental Term Loan B borrowings of up to $425.0 million, taking the Term Loan B to $1,272.4 million. Proceeds net of discount were $391.0 million. Source
  • Ended: Term Loan A future borrowing commitments were reduced to zero, so no further borrowings can be drawn under that facility. Source

Results and earnings

  • Net loss and EPS in quarter: The company reported revenues of $470.5 million, a net loss of $197.4 million, diluted EPS of $(0.73) and Adjusted EBITDA of $82.3 million. Revenues were $679.0 million in the fourth quarter of 2024 and $690.3 million in the first quarter of 2024.
  • Adjusted EBITDA described as core earnings: Management said the $82 million of Adjusted EBITDA consists entirely of core earnings from terminal and vessel operations, without one-time gains from prior periods.
  • Operating cash flow turned negative: Cash used in operating activities was $31.7 million, compared with $70.1 million provided in the first quarter of 2024. The net loss, adjusted for non-cash items, rose $358.5 million, offset by higher accounts payable. Source

Segments and volumes

  • Terminals margin fell on novation: Terminals and Infrastructure segment operating margin was $74.6 million, against $206.1 million in the fourth quarter of 2024. The fourth quarter included $235.6 million of novation income, which did not recur. Source
  • Downstream volumes fell on maintenance: Volumes delivered to downstream terminal customers were 13.8 TBtu, down from 18.4 TBtu in the fourth quarter of 2024 and 22.0 TBtu in the first quarter of 2024. The company attributed the decline to maintenance at Old Harbour and San Juan. Source
  • Ships revenue slightly lower: Ships segment revenue was $38.6 million and segment operating margin $31.4 million. A vessel was moved to terminal use after its third-party charter ended in the fourth quarter of 2024. Source

“We are confident that Excelerate will continue NFE’s vision of providing reliable and cost-effective energy to Jamaica”

Wes Edens, Chairman and CEO of New Fortress Energy

Pricing and cargo sales

  • Cargo sales added revenue: Revenue from cargo sales was $182.7 million, up from $91.9 million in the fourth quarter of 2024. Cargo sales costs were $103.8 million. Source
  • Henry Hub index rose: The Henry Hub index used to invoice downstream customers was up 31% from the fourth quarter of 2024 and up 63% from the first quarter of 2024. Source
  • Gas purchase cost per MMBtu rose: The weighted average cost of gas purchased was $9.57 per MMBtu, up from $8.75 in the fourth quarter of 2024. Source

Costs, interest and margins

  • Interest expense rose sharply: Interest expense was $213.7 million, up $114.2 million from the fourth quarter of 2024. Less interest was capitalized, $74.1 million compared with $139.5 million, as the Fast LNG project and Santa Catarina facility entered service. Source
  • Operating costs rose on new plants: Operations and maintenance expense was $55.0 million, up $20.5 million from the fourth quarter. The increase was attributed to payroll, maintenance and logistics for the Fast LNG and Santa Catarina facilities placed into service in 2024. Source
  • Currency remeasurement gain: Other income was $63.9 million, mainly foreign currency remeasurement gains on Brazilian real strength against the U.S. dollar. Source
  • Depreciation rose on new assets: Depreciation and amortization was $53.1 million, up $14.3 million from the fourth quarter, mainly from the Fast LNG project and Santa Catarina facility. Source
  • Tax provision lower than prior quarter: The tax provision was $28.7 million, against $41.5 million in the fourth quarter of 2024. Management linked it to the expected gain on the Jamaica sale and Brazil foreign earnings. Source

“We have a number of notable one time events such as the FEMA claim, FSRU sub charters, and the Genera incentive payment that we expect will boost remaining earnings through 2025.”

New Fortress Energy Inc.

Capital, cash and shareholder returns

  • Investing outflow funded by borrowing: Investing cash outflow was $335.9 million, including $340.5 million of capital expenditures. Total borrowings were $943.6 million, used mainly for the onshore FLNG project and corporate expenses. Source
  • Total cash balance and restricted share: Total cash was $827 million at March 31, 2025, of which $448 million was unrestricted.
  • Dividends restricted by intercompany agreements: Dividends of $3.5 million were paid in the quarter. Intercompany agreements from the fourth quarter 2024 refinancing bar the parent from paying dividends to shareholders. Source

Liquidity and covenants

  • Liquidity judged insufficient in full: Under the going-concern assessment, management concluded that current liquidity and forecast operating cash flows are not sufficient in full to meet obligations as they become due, excluding planned asset sales. Source
  • Liquidity plan approved: Management has approved a plan to alleviate liquidity risk. Its assessment of whether liquidity will be sufficient over the next twelve months is still in progress. Source
  • Asset sale sweep waived: The Twelfth Amendment removes the requirement that 75% of net proceeds from certain asset sales repay debt, which had applied to Jamaica sale proceeds. Source
  • Vendor payment terms extended: Management said relationships with vendors, including those building the Fast LNG assets, let the company extend payment terms to match the first Fast LNG project's completion. Source
  • Fixed charge coverage covenant added: The Fifth Amendment added a fixed charge coverage ratio covenant to the Term Loan A and removed the debt-to-capitalization covenant. Source

Projects and development

  • Brazil power plants under construction: The 624 MW CELBA plant was about 95% complete and the adjacent PortoCem plant over 50% complete. Both projects are fully funded with asset-level debt already in place.
  • First Fast LNG unit fully commissioned: The first Fast LNG unit has been fully commissioned. Management is increasing available liquefaction capacity through optimization projects. Source
  • Klondike data center venture: Klondike, launched in 2024, develops power and data center infrastructure for hyperscale customers, with more than 1,000 acres of developable land in Brazil, Ireland and the United States. Source
  • Puerto Sandino timing undetermined: Construction of the Puerto Sandino terminal and power plant is substantially complete. Commissioning timing will depend on the most optimal use of the LNG supply chain. Source

Regulatory matters and claims

  • PREPA claim for $659 million: The company is pursuing a $659 million request for equitable adjustment tied to early termination of its emergency power contract with PREPA. The amount and timing of any recovery are uncertain. Source
  • FERC environmental review under way: FERC issued a notice of intent to prepare an Environmental Impact Statement for the San Juan Facility, with public scoping sessions held in Puerto Rico in November 2024. Source

Coming up, as management said on 18 June 2025

  • Escrow proceeds due on release dates: An additional $99 million of Jamaica sale proceeds is held in escrow and returns to the company on release dates set in the sale agreement. Source
  • Brazil power auctions expected 2025: Management expects to take part in Brazil power auctions anticipated in 2025, and would build a gas plant using Santa Catarina gas if successful. Source
  • PREPA gas agreement expires June 2025: The island-wide gas sale agreement with PREPA expires in June 2025, and the company is in active discussions on an extension. Source
  • Coast Guard letter expected imminently: The company is working with the Coast Guard to obtain a new Letter of Recommendation to FERC, which management expects shortly. Source
  • Asset-based financing planned: Following the Jamaica sale, management plans a potential asset-based financing similar to other liquefier financings, using its LNG terminal and contract portfolio.

Risks management discussed

  • Financial: Liquidity may not cover obligations as they fall due, and the going-concern assessment excludes planned asset sales. Source
  • Financial: Liquidity depends on the company's ability to keep extending vendor payment terms and other obligations in future periods. Source
  • Financial: Debt agreements contain restrictive covenants limiting operations, refinancing, and certain transactions. Source
  • External: Geopolitical events and volatility in gas and LNG markets may affect pricing and supply. Source
  • Regulatory: The PREPA claim recovery amount and payment timing may differ materially from management's current estimate. Source
  • Regulatory: The Ireland LNG terminal and power plant development is uncertain, with regulatory risks that could prevent it going ahead. Source

Earlier plans management reported on

  • Met: Management said it would use sale proceeds to pay down $270 million of the Revolving Credit Facility and $55 million of Term Loan A. The amended agreements record that both repayments were made. Source
  • On track: Management states both Brazil power plant projects are on time and on budget, with CELBA expected to start earnings in the third quarter.
  • Met: The first Fast LNG unit is described as fully commissioned, with optimization projects under way to increase liquefaction capacity. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.