What management said about Q4 FY2026, from the documents filed with the SEC on 26 March 2026: press release. The quarter’s numbers.

Key takeaways

  • Fourth quarter revenue and profit rose: Revenues rose 12.7% to $262.1 million. Net income was $49.2 million, or $3.47 per diluted share, compared with $31.4 million, or $2.22, a year earlier. Source
  • Fiscal year earnings and revenue higher: Fiscal 2026 revenues were $944.6 million, up 8.1%. Net income was $137.8 million, or $9.74 per diluted share, against $85.5 million, or $6.15, in fiscal 2025. Source
  • Gross margin reached 25.0%: Gross profit was $65.6 million, or 25.0% of revenues, against 20.5% in the prior-year quarter. Fiscal 2026 gross margin was 20.5%, against 16.1%. Source
  • Backlog near $2.9 billion: Consolidated project backlog was approximately $2.9 billion at January 31, 2026, against approximately $1.4 billion a year earlier. The prior release gave approximately $3.0 billion at October 31, 2025. Source
  • $2.5 billion of contract value added: During fiscal 2026 the company added $2.5 billion of new contract value, which management said increased backlog to more than $2.9 billion at year-end. Source
  • Grid pressure cited as demand driver: Management named AI and data center growth, electrification, replacement of aging plants and underinvestment in power infrastructure as pressures on power grids. Source
  • Cash and investments reached $895.0 million: Cash, cash equivalents and investments were $895.0 million, against $525.1 million a year earlier. Management said the company continues to generate significant cash flow. Source

“Our record fourth quarter performance capped a year of strong execution throughout fiscal 2026, driving record top and bottom-line performance for the full year.”

David Watson, President and Chief Executive Officer of Argan

What changed from last quarter

  • New: The Trumbull Energy Center reached substantial completion earlier than planned. The prior release, for the third quarter, did not mention this milestone. Source

Results and growth drivers

  • Fourth quarter revenue and profit rose: Revenues rose 12.7% to $262.1 million. Net income was $49.2 million, or $3.47 per diluted share, compared with $31.4 million, or $2.22, a year earlier. Source
  • Fiscal year earnings and revenue higher: Fiscal 2026 revenues were $944.6 million, up 8.1%. Net income was $137.8 million, or $9.74 per diluted share, against $85.5 million, or $6.15, in fiscal 2025. Source
  • Power revenue from newly awarded contracts: Power segment revenue increased as recently awarded contracts moved through early construction. The company said this produced revenue that was not present in the prior-year period. Source

Segments and businesses

  • Revenue rose in every segment: Management said the year-over-year revenue increase reflected higher revenues in all of the company's business segments. Segment-level figures are not given in the release. Source
  • Roberts Company described as industrial services: The Roberts Company is described as a fully integrated industrial construction, fabrication and plant services company. Source
  • SMC described as teledata services: SMC Infrastructure Solutions is described as providing teledata infrastructure services. The prior release described the same business as providing telecommunications infrastructure services. Source

“These are exciting times for our company as demand for our services remains exceptionally strong.”

David Watson, President and Chief Executive Officer of Argan

Products and customers

  • Gas-fired and renewable plant construction: Gemma Power Systems and Atlantic Projects Company focus on engineering, procurement and construction of natural gas-fired power plants and renewable energy facilities. Source
  • Established customer base cited: Management pointed to its longstanding customer base, its execution record, and its experience building large, complex power generating facilities. Source
  • Pipeline of gas-fired plant opportunities: Management said it is seeing a pipeline of projects to build new gas-fired power plants that deliver reliable power on a 24/7 basis. Source

Costs, margins and pricing

  • Gross margin reached 25.0%: Gross profit was $65.6 million, or 25.0% of revenues, against 20.5% in the prior-year quarter. Fiscal 2026 gross margin was 20.5%, against 16.1%. Source
  • Power margin gain tied to execution: Management attributed the Power segment margin improvement to strong project execution, including early substantial completion at the Trumbull Energy Center. Source
  • Selling and administrative costs rose: Selling, general and administrative expenses were $17.9 million, or 6.8% of revenues, against $14.9 million, or 6.4%, in the prior-year quarter. Source

“we remain as disciplined today as we were in our first year in the way we pursue opportunities and deliver successful project outcomes for our customers, employees, and shareholders.”

David Watson, President and Chief Executive Officer of Argan

Demand and the order book

  • Backlog near $2.9 billion: Consolidated project backlog was approximately $2.9 billion at January 31, 2026, against approximately $1.4 billion a year earlier. The prior release gave approximately $3.0 billion at October 31, 2025. Source
  • $2.5 billion of contract value added: During fiscal 2026 the company added $2.5 billion of new contract value, which management said increased backlog to more than $2.9 billion at year-end. Source
  • Demand described as exceptionally high: Management said demand for its services remains exceptionally high. Source
  • Grid pressure cited as demand driver: Management named AI and data center growth, electrification, replacement of aging plants and underinvestment in power infrastructure as pressures on power grids. Source

Earnings measures and other income

  • EBITDA rose to $56.0 million: EBITDA was $56.0 million, against $39.3 million a year earlier. EBITDA was 21.4% of revenues, against 16.9%. Source
  • Fiscal EBITDA reached $162.8 million: Fiscal 2026 EBITDA was $162.8 million, up $49.3 million from fiscal 2025. Source
  • Other income from investment earnings: Other income, net, was $7.7 million in the quarter, which the company said mainly reflected investment income. Source
  • EBITDA is a non-GAAP measure: The release reconciles EBITDA, a non-GAAP measure, to the comparable GAAP measures in tables at the end of the release. Source

Capital, cash and share count

  • Cash and investments reached $895.0 million: Cash, cash equivalents and investments were $895.0 million, against $525.1 million a year earlier. Management said the company continues to generate significant cash flow. Source
  • Net liquidity up, no debt: Net liquidity was $421.0 million, against $301.4 million, and the company had no debt. Source
  • Treasury shares reduced, outstanding shares up: Treasury shares fell to 1,877,577 from 2,194,075, and treasury stock at cost rose to $114.4 million from $105.6 million. Shares outstanding rose to 13,950,712 from 13,634,214. Source

Strategy and investment

  • Discipline in project selection: Management said it remains as disciplined as in its first year in how it pursues opportunities and delivers project outcomes for customers, employees and shareholders. Source
  • Positioned for energy infrastructure demand: Management said the company is positioned to capitalize on demand for reliable, high-performing energy infrastructure. Source
  • Growth and profitability targeted for years: Management said it is focused on continued revenue growth and higher profitability in the years ahead. Source

Figures management reported

FigureReported
Consolidated project backlog Sourceapproximately $2.9 billion
New contract value added in fiscal 2026 Source$2.5 billion

Earlier plans management reported on

  • Ahead: Management said the Trumbull Energy Center reached substantial completion early. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.