Terawulf Inc.: Q2 FY2026 earnings call

What management said about Q2 FY2026, from the documents filed with the SEC on 5 August 2026: press release. Guidance figures: 1 lowered, 5 new, 3 kept. The quarter’s numbers.

Key takeaways

  • HPC lease share reached 71%: Second-quarter revenue was $44.8 million, of which $31.9 million was HPC lease revenue, about 71% of the total. Digital asset revenue was $12.8 million. Source
  • Net loss included warrant revaluation charge: Net loss attributable to TeraWulf was $939.9 million, or $1.94 per share, against $18.4 million, or $0.05, a year earlier. The change in fair value of warrants was a $755.7 million loss. Source
  • Lake Mariner reached 102 MW after CB-3: 81 MW of revenue-generating critical IT capacity was operating at Lake Mariner on June 30, 2026. CB-3 delivery in early July raised this to 102 MW, with 336 MW more under construction across CB-4 and CB-5. Source
  • Anthropic lease adds 20-year contract: The Anthropic lease at Justified runs 20 years, with about $19 billion of contracted revenue over the initial term and up to about $33 billion if both five-year extensions are exercised. Source
  • Adjusted EBITDA was negative: Non-GAAP Adjusted EBITDA was $(18.3) million in the quarter, against $14.5 million a year earlier. Six-month Adjusted EBITDA was $(22.4) million, against $9.8 million. Source
  • Cash held near $3.0 billion: Cash and restricted cash were about $3.0 billion at quarter-end, against $3.1 billion at March 31, 2026. Source
  • Abernathy stake sale for $530 million: The company agreed to sell its entire 50.1% Abernathy interest for about $530 million in cash. Source

“The second quarter demonstrates that TeraWulf is moving from platform formation to scaled execution.”

Paul Prager, Chairman and Chief Executive Officer of TeraWulf

Guidance

AreaPeriodFigureAgainst last quarter
Contracted critical IT capacity Sourceannual, ongoing250 MW to 500 MW of incremental critical IT capacity annuallyKept
WULF Compute build cost Sourceper critical IT MW$8-10 million per critical IT MWKept
CB-4 delivery and rent commencement Sourcesecond half of 2026phased delivery and rent commencement during the second half of 2026Kept
CB-5 phased delivery Sourceearly 2027begin phased delivery in early 2027Lowered from CB-5 delivery and rent commencement in 2026
Justified (Anthropic lease) delivery Sourcesecond half of 2027 to early 2028initial delivery in the second half of 2027; full delivery in early 2028New
Muskie initial electric service Sourcefourth quarter of 2028fourth quarter of 2028New
Chesapeake initial data center operations Source20302030New
Lake Hawkeye operations Sourceapproximately 2029approximately 400 MW gross, or approximately 320 MW critical IT; operations approximately 2029New
Lake Mariner incremental power Sourcenot stated250 MWNew

What changed from last quarter

  • New: A 20-year Anthropic lease for about 401 MW of critical IT capacity at Justified was entered into after quarter-end. Source
  • New: The Muskie Data Campus was acquired in May 2026, covering about 308 acres in Eastern Kentucky. Source
  • New: Electric service and infrastructure agreements with Kentucky Power Company were entered into for up to 1 GW. Source
  • New: An agreement was entered into to sell the entire 50.1% Abernathy Joint Venture interest for about $530 million in cash. Source
  • New: FERC authorized the pending Morgantown acquisition on July 29, 2026. Source
  • New: Google credit support of $600 million for Fluidstack lease obligations becomes effective once CB-3 delivery conditions are satisfied. Source
  • Guidance lowered: CB-5 phased delivery timing moved to early 2027 from 2026 delivery and rent commencement in the prior release. Source
  • Guidance kept: The annual target of contracting 250 MW to 500 MW of incremental critical IT capacity was reaffirmed. Source

Results and growth drivers

  • HPC lease share reached 71%: Second-quarter revenue was $44.8 million, of which $31.9 million was HPC lease revenue, about 71% of the total. Digital asset revenue was $12.8 million. Source
  • Revenue below prior-year quarter: Total revenue was $44.8 million, against $47.6 million in the second quarter of 2025. Six-month revenue was $78.8 million, against $82.0 million a year earlier. Source
  • Net loss included warrant revaluation charge: Net loss attributable to TeraWulf was $939.9 million, or $1.94 per share, against $18.4 million, or $0.05, a year earlier. The change in fair value of warrants was a $755.7 million loss. Source
  • Operating loss widened: The operating loss was $140.5 million, against $15.6 million in the prior-year quarter. Source

Platform sites and build-out

  • Lake Mariner reached 102 MW after CB-3: 81 MW of revenue-generating critical IT capacity was operating at Lake Mariner on June 30, 2026. CB-3 delivery in early July raised this to 102 MW, with 336 MW more under construction across CB-4 and CB-5. Source
  • Justified campus in Kentucky: Justified in Hawesville has access to up to about 480 MW of gross power, an energized on-site substation and more than 250 buildable acres. It is the site of the Anthropic lease. Source
  • Chesapeake site has operating capacity: Chesapeake in Morgantown, Maryland has about 210 MW of operational grid-connected capacity and substantial electrical infrastructure, with expansion potential. Source
  • Lake Hawkeye redevelopment site: Lake Hawkeye is a leased 183-acre former industrial site with existing electrical infrastructure, described as a longer-term redevelopment. Source

“This is an important credit milestone that further strengthens the contracted revenue profile of the Lake Mariner buildout.”

Patrick Fleury, Chief Financial Officer of TeraWulf

Customers and lease contracts

  • Anthropic lease adds 20-year contract: The Anthropic lease at Justified runs 20 years, with about $19 billion of contracted revenue over the initial term and up to about $33 billion if both five-year extensions are exercised. Source
  • Fluidstack lease backed by Google: Google credit support of $600 million for Fluidstack lease obligations depends on CB-3 delivery, which management reports as completed. Source
  • Credit milestone framed as contracted revenue: The CFO described the Google support as an important credit milestone for the contracted revenue profile of Lake Mariner. Source

Operating costs and expenses

  • SG&A expense rose from prior year: Selling, general and administrative expenses were $112.4 million, plus $14.5 million to related parties, against $10.0 million and $4.3 million a year earlier. Source
  • Stock-based compensation rose to $83.9 million: Stock-based compensation expense was $83.9 million in the quarter, against $1.3 million a year earlier. The company excludes it from Adjusted EBITDA. Source
  • Interest expense far above prior year: Interest expense was $56.4 million, against $4.0 million a year earlier, and interest income was $29.0 million. Source
  • Depreciation and operating costs increased: Depreciation was $21.2 million, against $18.8 million, and operating expenses were $21.7 million, against $2.0 million a year earlier. Source

“We are prepared to realize value where appropriate and redeploy capital toward larger-scale”

Paul Prager, Chairman and Chief Executive Officer of TeraWulf

Margins and Adjusted EBITDA

  • Adjusted EBITDA was negative: Non-GAAP Adjusted EBITDA was $(18.3) million in the quarter, against $14.5 million a year earlier. Six-month Adjusted EBITDA was $(22.4) million, against $9.8 million. Source
  • First-quarter Adjusted EBITDA was negative: The prior release reported Adjusted EBITDA of $(4.1) million for the first quarter, about $14.3 million higher than the second-quarter figure.
  • Cost of revenue fell from prior year: Cost of revenue, excluding depreciation, was $12.4 million, against $22.1 million a year earlier. Source

Capital, cash and asset sale

  • Cash held near $3.0 billion: Cash and restricted cash were about $3.0 billion at quarter-end, against $3.1 billion at March 31, 2026. Source
  • Abernathy stake sale for $530 million: The company agreed to sell its entire 50.1% Abernathy interest for about $530 million in cash. Source
  • Net proceeds from share sales: Net proceeds from common stock issuance were $1.20 billion in the six months to June 30, against none a year earlier. Source
  • Capital tied to contracted demand: Management said it matches capital deployment to contracted demand and selectively recycles capital when that improves control, scale and long-term returns. Source

Strategy and development model

  • Repeatable model across the platform: Management described a repeatable model of controlling power-advantaged infrastructure, securing long-duration customer contracts and delivering capacity in phases. Source
  • Platform widened beyond Lake Mariner: The company is expanding its national platform beyond Lake Mariner, focusing on power-advantaged sites for large-scale, phased HPC development. Source
  • Phased capacity converted to recurring revenue: Management said the company delivered additional contracted capacity at Lake Mariner and converted it into recurring lease revenue. Source

Coming up, as management said on 5 August 2026

  • Morgantown closing pending conditions: Closing of the Morgantown acquisition remains subject to the remaining closing conditions and required approvals. Source
  • Abernathy sale closing: The release reports the sale agreement but does not give a closing date. Source
  • CB-4 rent commencement later in 2026: The first CB-4 data hall is in commissioning, with rent commencement expected in the second half of 2026. Source

Figures management reported

FigureReported
Revenue-generating critical IT capacity, Lake Mariner Source81 MW at June 30, 2026; 102 MW after CB-3 delivery in early July 2026
Critical IT capacity under construction Source336 MW across CB-4 and CB-5
Contracted critical IT capacity, Anthropic lease at Justified Sourceapproximately 401 MW over a 20-year term
Contracted revenue, Anthropic lease Sourceapproximately $19 billion over initial term; up to approximately $33 billion with both extensions
HPC lease revenue Source$31.9 million, approximately 71% of total revenue
WULF Compute build cost Source$8-10 million per critical IT MW

Risks management discussed

  • Operational: Management expects the 336 MW under construction to be delivered within cost and schedule guidance; the release gives no detail on contingency. Source
  • Regulatory: Lake Hawkeye's potential is subject to permitting and site development, which management names as conditions. Source
  • External: Management said access to power has become the defining constraint on AI infrastructure development. Source

Earlier plans management reported on

  • Met: Management reports CB-3 delivery completed in early July, which satisfied the conditions for the Google credit support. Source
  • Met: The prior release said the acquisition remained subject to customary approvals including FERC; the current release reports FERC authorization received. Source
  • Not stated: The prior release said CB-4 and CB-5 remained on schedule for 2026; this release moves CB-5 phased delivery to early 2027 and gives no status.
  • Not stated: The prior release targeted Abernathy delivery for the fourth quarter of 2026; this release reports an agreement to sell the interest and gives no delivery status.

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.