Venture Global, Inc.: Q1 FY2026 earnings call

What management said about Q1 FY2026, from the documents filed with the SEC on 12 May 2026: press release. Guidance figures: 1 raised, 1 narrowed, 3 kept. The quarter’s numbers.

Key takeaways

  • Revenue rose 59% on higher volumes: Revenue was $4,599 million against $2,894 million a year earlier. Income from operations was $1,151 million, up 7%, and net income attributable to common stockholders was $488 million, up 23%. Source
  • Plaquemines Phase I COD targeted Q4 2026: Plaquemines Phase I commercial operations are targeted for Q4 2026 and Phase II for mid 2027. Management cited mitigations and incremental spending for construction and commissioning challenges. Source
  • CP2 first LNG due second half 2027: Management said it remains on track to produce first LNG at CP2 in the second half of 2027, which it described as considerably faster from FID than any large-scale LNG project. Source
  • 84% of 2026 cargos now sold: Additional contracts bring 2026 sales to 84% of available cargos, at a weighted average liquefaction fee of $4.51/MMBtu. Five-year supply agreements now total over 3 MTPA. Source
  • Lower net LNG prices offset volume gains: LNG sales prices net of feed gas cost fell $1.9 billion, partly offsetting $1.8 billion of higher LNG sales volumes. Cost of sales rose to $2,784 million from $1,059 million. Source
  • CP2 Phase II reaches FID: Phase II of CP2 reached final investment decision and closed an $8.6 billion project financing, bringing total CP2 financing to $20.7 billion. Source

“The first quarter of 2026 was a dynamic, and at times volatile, period for the global LNG market, and we are proud that our company has played a critical role in helping maintain supply stability.”

Venture Global CEO Mike Sabel

Guidance

AreaPeriodFigureAgainst last quarter
Consolidated Adjusted EBITDA Sourcefull year 2026$8.2 - $8.5 billionRaised from $5.2 - $5.8 billion
Total cargo range Source2026494 - 523 cargosNarrowed from 486 - 527 cargos
Liquefaction fee assumption for unsold cargos Source2026$9.50/MMBtu - $10.50/MMBtu
Sensitivity to liquefaction fee Sourcefull year 2026$300 million - $350 million per $1.00/MMBtu change
Calcasieu Project cargo exports Source2026147 - 154 cargos
Plaquemines Project cargo exports Source2026347 - 369 cargos
Plaquemines Phase I commercial operations date SourceQ4 2026Q4 2026Kept
Plaquemines Phase II commercial operations date Sourcemid 2027mid 2027Kept
CP2 first LNG production Sourcesecond half of 2027second half of 2027Kept
Non-controlling interest share of Consolidated Adjusted EBITDA Source2026$160 million - $180 million

What changed from last quarter

  • Guidance raised: Consolidated Adjusted EBITDA guidance for 2026 was raised to $8.2 - $8.5 billion from $5.2 - $5.8 billion. Source
  • Guidance raised: The midpoint of the 2026 cargo range was raised, and the range was narrowed to 494 - 523 from 486 - 527. Source
  • New: CP2 Phase II reached final investment decision, with an $8.6 billion project financing closed and total CP2 financing at $20.7 billion. Source
  • New: A new binding agreement with TotalEnergies covers about 0.85 MTPA of LNG for about five years starting in 2026. Source
  • New: Venture Global Calcasieu Pass issued $750 million of 6.0% senior secured notes due 2036. Source

Results and growth drivers

  • Revenue rose 59% on higher volumes: Revenue was $4,599 million against $2,894 million a year earlier. Income from operations was $1,151 million, up 7%, and net income attributable to common stockholders was $488 million, up 23%. Source
  • Net income gain tied to operations: The company tied the $92 million increase in net income mainly to income from operations up $71 million, driven by $1.8 billion of higher LNG sales volumes at Plaquemines during commissioning. Source
  • Adjusted EBITDA up 2%: Consolidated Adjusted EBITDA was $1,372 million, up from $1,346 million, mainly on higher volumes and lower development expense, partly offset by lower net LNG sales prices. Source
  • Diluted EPS rose to $0.19: Diluted EPS was $0.19 against $0.15 a year earlier, and basic EPS was $0.20 against $0.17. Diluted weighted average shares were 2,635 million, against 2,643 million. Source

Project status and commissioning

  • Plaquemines Phase I COD targeted Q4 2026: Plaquemines Phase I commercial operations are targeted for Q4 2026 and Phase II for mid 2027. Management cited mitigations and incremental spending for construction and commissioning challenges. Source
  • Volumes at a new quarterly record: The company exported 130 cargos and sold 481 TBtu of LNG in the quarter, a new quarterly record for Venture Global. Cargo exports were 63 in the prior-year quarter. Source
  • Calcasieu Pass reached one year: Calcasieu Pass reached one year since its commercial operations date in April, and the company said it had no cargo shortfalls over that period. Source
  • CP2 construction milestones reached: Two of the four LNG storage tanks at CP2 have roofs raised, the perimeter wall is watertight, and 12 of 36 liquefaction trains are on their foundations. Source
  • CP2 first LNG due second half 2027: Management said it remains on track to produce first LNG at CP2 in the second half of 2027, which it described as considerably faster from FID than any large-scale LNG project. Source

“We are making significant progress on construction at our third facility, CP2, including raising the roofs of our first two LNG tanks this quarter and successfully closing an $8.6 billion FID for Phase II of that project.”

Venture Global CEO Mike Sabel

Contracts and customers

  • 84% of 2026 cargos now sold: Additional contracts bring 2026 sales to 84% of available cargos, at a weighted average liquefaction fee of $4.51/MMBtu. Five-year supply agreements now total over 3 MTPA. Source
  • Vitol and TotalEnergies agreements expanded: The five-year Vitol agreement was increased to about 1.7 MTPA from 1.5 MTPA. TotalEnergies agreed to buy about 0.85 MTPA for about five years from 2026. Source
  • Hanwha and Trafigura deals announced earlier: Three additional LNG SPAs signed in Q1 2026 were previously announced, including a 20-year SPA with Hanwha Aerospace. Five-year binding agreements with Trafigura and Vitol were also previously announced. Source

Margins, pricing and feed gas

  • Lower net LNG prices offset volume gains: LNG sales prices net of feed gas cost fell $1.9 billion, partly offsetting $1.8 billion of higher LNG sales volumes. Cost of sales rose to $2,784 million from $1,059 million. Source
  • Development expense fell sharply: Development expense was $46 million, down from $182 million. Interest rate swaps moved to a $15 million gain from a $192 million loss a year earlier. Source
  • Operating costs little changed: Operating and maintenance expense was $270 million against $252 million, and general and administrative expense was $97 million against $105 million. Source

“We are continuing the safe startup and commissioning of Plaquemines LNG and are reaffirming our expectation of achieving Phase I commercial operations later this year.”

Venture Global CEO Mike Sabel

Capital and financing

  • CP2 Phase II reaches FID: Phase II of CP2 reached final investment decision and closed an $8.6 billion project financing, bringing total CP2 financing to $20.7 billion. Source
  • Stonepeak preferred interests redeemed: Calcasieu Pass Funding closed a $1.75 billion senior secured term loan B in April, used to redeem preferred equity interests issued to Stonepeak Bayou Holdings II. Source
  • Construction loan prepaid with notes: The $750 million 6.0% notes due 2036 were issued by Venture Global Calcasieu Pass, and the net proceeds prepaid the remaining construction term loan balance at the Calcasieu Pass facility. Source

Balance sheet and cash

  • Total assets reached $56.3 billion: Total assets were $56,300 million at March 31, 2026, up from $53,446 million at December 31, 2025. Property, plant and equipment, net, was $49,754 million. Source
  • Cash fell, restricted cash rose: Cash and cash equivalents were $1,599 million, down from $2,355 million at December 31, 2025. Restricted cash was $335 million current and $1,117 million noncurrent. Source
  • Long-term debt rose to $36.5 billion: Long-term debt, net, was $36,456 million, up from $33,393 million, and the current portion fell to $126 million from $812 million. Source

Equity and preferred dividends

  • Class A shares rose to 514 million: Class A common stock outstanding was 514 million at March 31, 2026, up from 488 million at December 31, 2025, while Class B stayed at 1,969 million. Source
  • VGLNG preferred dividends unchanged: Dividends on VGLNG Series A Preferred Shares were $68 million in both periods. Net income attributable to redeemable stock of subsidiary was $42 million. Source

Coming up, as management said on 12 May 2026

  • Plaquemines Phase I COD in Q4 2026: Management is targeting Phase I commercial operations in Q4 2026, after commissioning, assurance testing and any required remediation. Source
  • Plaquemines Phase II COD in mid 2027: Phase II commercial operations are targeted for mid 2027. Source
  • CP2 first LNG in second half 2027: CP2 is expected to produce first LNG in the second half of 2027. Source

Risks management discussed

  • Operational: Management cited construction and commissioning challenges on a large, complex project, addressed through mitigations and incremental expenditures. Source
  • Operational: The Plaquemines Phase I COD target depends on completing commissioning and assurance testing and any required remediation or rectification work. Source
  • Financial: Interest expense rose $168 million, and this was partly offset by lower net LNG sales prices. Source
  • External: Management stated that changes in domestic and international natural gas prices could affect the 2026 Consolidated Adjusted EBITDA guidance. Source
  • External: Management said it is navigating the ongoing impacts of the Middle East conflict on the market. Source
  • Demand: Management described the first quarter LNG market as dynamic and at times volatile. Source

Earlier plans management reported on

  • On track: Management said it remains on track for first LNG at CP2 in the second half of 2027. Source
  • Not stated: Management reaffirmed the Q4 2026 Phase I target after citing mitigations and incremental expenditures. Source
  • Not stated: The company said Calcasieu Pass reached one year since its commercial operations date in April with no cargo shortfalls. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.