Open the filing on EDGARFervo Energy Company811 Main St, 1700Houston, TX 77002 in just 21 days spud-to-total-depth, a new Company record for drilling pace on its most complex well design to FORWARD-LOOKING STATEMENTS CONDENSED CONSOLIDATED STATEMENTS OF OPERATIONS (UNAUDITED) CONDENSED CONSOLIDATED BALANCE SHEETS (UNAUDITED) CONTACTS FINANCIAL HIGHLIGHTS date. (Dollars and shares in thousands)As of June 30, As of December 31,20262025ASSETSCurrent assets:Cash and cash equivalents ....................................................................................................$2,106,371$461,836Grant receivables ..................................................................................................................17,17710,580Prepaid expenses and other ..................................................................................................30,6349,714Total current assets ..........................................................................................................2,154,182482,130Deposits ................................................................................................................................12,60215,234Construction-in-process .......................................................................................................1,235,160789,571Operating leases right-of-use assets .....................................................................................88,66758,713Restricted cash ......................................................................................................................11,0006,000Other long-term assets...........................................................................................................33,47813,520Total assets ......................................................................................................................$3,535,089$1,365,168LIABILITIES AND EQUITYCurrent liabilities:Accounts payable .....................................................................................................................$29,667$10,789Accrued capital expenditures...................................................................................................173,961119,303Current portion of long-term debt............................................................................................11,042 - Operating lease liabilities .......................................................................................................24,7444,822Other current liabilities ...........................................................................................................10,61416,997Total current liabilities .......................................................................................................250,028151,911Long-term debt, net of issuance costs and current portion ......................................................217,376172,837Operating lease liabilities .......................................................................................................85,12372,639Other long-term liabilities .......................................................................................................1,74911,407Total liabilities ................................................................................................................554,276408,794Commitments and Contingencies (Note 19)............................................................................Mezzanine equityRedeemable convertible preferred stock, par value $0.0001 per share; 0 and 283,546 authorized; 0 and 279,995 issued and outstanding as of June 30, 2026 and December 31, 2025 ... - 1,022,942Redeemable noncontrolling interestCape Phase I HoldCo - Redeemable noncontrolling interest ................................................105,118102,586Cape Phase I Intermediate HoldCo - Redeemable noncontrolling interest...........................81,85877,344Stockholders’ equity (deficit):Common stock, par value $0.0001 per share; 0 and 358,279 authorized; 0 and 9,457 issued as of June 30, 2026 and December 31, 2025, respectively(1) ............................................... - 1Class A common stock, par value $0.0001 per share; 1,000,000 and 0 authorized; 286,869 and 0 issued as of June 30, 2026 and December 31, 2025, respectively .............................29 - Class B common stock, par value $0.0001 per share; 40,000 and 0 authorized; 7,785 and 0 issued as of June 30, 2026 and December 31, 2025, respectively .......................................1 - Additional paid-in capital 3,126,084 - Treasury stock, at cost; 0 shares and 270 shares as of June 30, 2026 and December 31, 2025, respectively(1) ................................................................................................................. - (1,960)Accumulated deficit ................................................................................................................(332,277)(244,539)Total stockholders’ equity (deficit) .......................................................................................2,793,837(246,498)Total liabilities, mezzanine equity, and stockholders’ equity (deficit) ............................$3,535,089$1,365,168 This press release contains “forward-looking statements” within the meaning of Section 27A of the Securities Act (Dollars and shares in thousands except per share amounts)Three Months Ended June 30,Six Months Ended June 30,2026202520262025Revenues ..........................................................................$113$ - $174$ - Costs and expenses:Operation and maintenance .........................................306158788410Research and development (income) expense, net .......(712)395(784)359General and administrative expense .............................27,4279,48444,41717,163Operating lease expense ...............................................1,4902054,1102,194Depreciation and amortization......................................34456437103Operating loss ..............................................................(28,742)(10,298)(48,794)(20,229)Other income (expense):Interest income ...............................................................10,52160113,3362,629Interest expense ..............................................................(2,215)(1,739)(4,932)(2,966)Other non-operating expense, net ...................................(35,478) - (47,354)(16)Loss before income taxes ..................................................(55,914)(11,436)(87,744)(20,582)Income tax expense ...........................................................(1)(2)(1)(2)Net loss ...........................................................................$(55,915)$(11,438)$(87,745)$(20,584)Net loss per share information: .......................................Net loss ........................................................................$(55,915)$(11,438)$(87,745)$(20,584)Less: Remeasurement of redeemable noncontrolling interest ..........................................................................(3,612)(189)(7,046)(189)Net loss attributable to common stock, basic and diluted ..........................................................................(59,527)(11,627)(94,791)(20,773)Weighted average common stock, basic and diluted (1)...................................................................157,0038,84483,6438,902Net loss per share attributable to common stockholders, basic and diluted (1) .............................$(0.38)$(1.31)$(1.13)$(2.33) Investor Relations •Marked its debut as a public company in the second quarter of 2026, completing its IPO and raising The drilling performance of the Sawtooth 7 well, combined with its design and resource temperature, underpins and Section 21E of the Exchange Act, which involve risks, uncertainties, and assumptions. All statements, other investor.relations@fervoenergy.com approximately $2.2 billion in gross proceeds. Fervo's confidence in its cost trajectory. Based on progress to date, Fervo continues to expect Phase II to achieve than statements of historical fact, are forward-looking statements. When used in this press release, the words •Reported Q2 2026 operating loss of $28.7 million and net loss of $55.9 million. an all-in cost of $5,500 per kilowatt, a key step toward its long-term target of $3,000 per kilowatt. “aim,” “anticipate,” “believe,” “continue,” “could,” “estimate,” “expect,” “forecast,” “future,” “guidance,” ICR, Inc. Fervo Energy Reports Second Quarter 2026 Results •Reported Q2 2026 capital expenditures of $226.5 million, compared to $108.0 million in Q2 2025, reflecting “intend,” “may,” “model,” “outlook,” “plan,” “positioned,” “potential,” “predict,” “project,” “seek,” “should,” Fervo@icrinc.com continued investment in Cape Station development and construction activities. Portfolio “target,” “will,” “would,” and similar expressions (including the negative of such terms) are intended to identify
- Expect total capital expenditures of approximately $850.0 to $900.0 million in the second half of 2026, in line Houston, TX - August 12, 2026 - Fervo Energy Company (“Fervo” or the “Company”) (NASDAQ: FRVO), the forward-looking statements, although not all forward-looking statements contain such identifying words. V2 Communications for Fervo Energy with previously disclosed expectations, reflecting continued construction activity at Cape Station as well as Fervo's development pipeline, which totaled more than 50 gigawatts as of quarter-end, continued to advance global pioneer of next-generation geothermal energy, today reported financial and operational results for the Although Fervo believes that the expectations and assumptions reflected in its forward-looking statements are fervo@v2comms.com broader pipeline development activities, including long-lead procurement and appraisal work across the during the second quarter. Approximately 400 megawatts moved from Early Development into Advanced second quarter ended June 30, 2026. reasonable as and when made, they involve risks and uncertainties that are difficult to predict and, in many cases, Company's GeoCluster portfolio. Development, driven by progress at one of the Company's leading prospects, where Fervo completed geological beyond Fervo’s control. Accordingly, forward-looking statements are not guarantees of future performance, and "Fervo continues to demonstrate the power of enhanced geothermal at scale," said Tim Latimer, CEO and Co- surveys, secured appraisal permits, initiated origination activities, and submitted an interconnection queue Fervo’s actual outcomes could differ materially from what Fervo has expressed in its forward-looking statements. BUSINESS UPDATES founder of Fervo. "We believe that demand for firm, carbon-free power has never been stronger, and our application. Separately, two additional GeoClusters totaling 10.5 gigawatts of capacity potential entered Early commercial pipeline reflects that - we're converting our extensive resource portfolio into shovel-ready capacity Development, following newly completed heat-initially-in-place studies by independent engineering firm Factors that could cause the outcomes to differ materially include (but are not limited to) the following: risks Commercial quarter after quarter. Alongside that growth, commissioning at Cape Station Phase I, record-setting drilling at DeGolyer and MacNaughton. Fervo also anticipates beginning an appraisal drilling program in Q4 2026. related to expanding our geothermal operations and accessing new markets; challenges in maintaining compliance Phase II, and continued derisking of our pipeline all bring Fervo closer to the goal of making geothermal the with extensive environmental regulations and permitting requirements; uncertainties in forecasting future Fervo continues to see robust commercial demand for firm, carbon-free power, driven by the scale of AI and data Fervo's current land portfolio spans over 650,000 acres. world's cheapest, most reliable form of power." operational results and growth due to economic conditions and market demand; compliance with environmental center build-out, the re-shoring of domestic manufacturing, and broader electrification straining existing grid regulations and climate change initiatives impacting operational costs; inherent risks in the geothermal industry, capacity. Buyers across categories - utilities, industrial offtakers, and hyperscale data center developers - Financing including potential operational disruptions and associated liabilities; the influence of consumer preferences, continue to seek out Fervo's 24/7 geothermal power as a differentiated solution to that demand, and the
BUSINESS AND OPERATIONAL HIGHLIGHTS
government policies, and competition on the demand for geothermal energy; risks associated with fluctuations in Company's commercial pipeline reflects that momentum. In May 2026, Fervo completed its initial public offering (IPO) and listed on Nasdaq. The IPO was significantly energy prices and material costs; dependence on a complex supply chain and successful maintenance of our upsized and priced well above the initial range, resulting in gross proceeds of approximately $2.2 billion,
- Continued to see strong growth in power demand across all categories of buyers, with behind-the-meter As part of its GeoCluster approach to AI data center development, Fervo is pursuing behind-the-meter delivery geothermal infrastructure; financial performance influenced by fluctuations in interest rates, capital availability, including the full exercise of the underwriters' over-allotment option. The IPO allows Fervo to accelerate its capabilities playing a growing role in meeting that demand outside conventional grid interconnection pathways in addition to conventional grid-delivered power purchase agreements - structures under which the and other market conditions; capacity actually constructed or for which we enter power purchase agreements strategic priorities, as the Company prepares to place over a gigawatt of capacity online by the end of the decade. timelines. Company delivers baseload power directly to a customer's on-site load, alongside ancillary energy systems under non-binding agreements, like the Geothermal Framework Agreement; exposure to legal proceedings and
- Raised its long-term development target to 1.1 gigawatts by 2030 - a 100-megawatt increase - as commercial developed by others, rather than through the grid. Fervo believes that behind-the-meter developments will serve claims arising from our business operations; protecting our brand reputation and facing potential negative public Earlier in the quarter, Fervo repaid all outstanding borrowings under the loan agreements with XRL ALC, LLC and technical confidence in the Company's pipeline continues to build. as a critical bridge for customers that urgently need power sooner than the grid can provide, and that these perception; negative public perception and political opposition impacting our ability to secure regulatory (the “XRC Facility”) using proceeds from the Project Granite Facility, the $421 million non-recourse project debt
- Advanced Cape Station Phase I toward commercial operation, achieving mechanical completion on developments will be connected to the grid over time. approvals and market acceptance; the successful and timely execution of our growth strategy, with risks of delays financing for the first phase of Cape Station that Fervo closed in Q1 2026, and the XRC Facility was terminated. GeoBlocks 1 and 2 and progressing commissioning, with GeoBlock 3 mechanical completion expected in the or failures; reliance on key personnel and the potential impact of labor costs and workforce challenges; heavy coming months. GeoBlock 1 first power is targeted for the fourth quarter of 2026, with full production Construction CONFERENCE CALL reliance on technology systems and potential cybersecurity threats; global economic and political conditions anticipated by year-end; GeoBlocks 2 and 3 are expected to reach initial power in early 2027. (1) Shares for periods presented have been retroactively adjusted to reflect the 0.7194-for-1 reverse stock split effected on May 14, 2026 in connection with affecting our operations, supply chain, and customer demand; the risk that our estimates of capacity potential and Cape Station Phase I is an approximately 100-megawatt installation comprising three 33-megawatt GeoBlocks. •Set a new company drilling record with Sawtooth 7 - the ninth Fervo 3.0 well and most complex well design the Company’s IPO. See Note 1 - Nature of Business and Note 2 - Significant Accounting Policies in the notes to condensed consolidated financial Fervo will host a conference call to discuss its second quarter 2026 business, operational and financial highlights heat initially in place are inaccurate or that we are unable to produce quantities of electrical energy commensurate statements for details. Fervo has achieved mechanical completion on GeoBlocks 1 and 2, with mechanical completion of GeoBlock 3 to date - reaching a measured depth of nearly 19,500 feet in a 460°F resource with a spud-to-total-depth of at 10:00 a.m. ET (9:00 a.m. CT) today, August 12, 2026. A live webcast of the conference call will be available in with such estimates; and other risks and uncertainties, including those set forth under “Risk Factors” in Fervo’s expected over the coming months. Commissioning on GeoBlock 1 continued throughout the quarter with the first just 21 days. the “Events” section of the Company’s investor relations website at ir.fervoenergy.com. A replay of the call will Registration Statement on Form S-1/A, filed with the Securities and Exchange Commission (the “SEC”) on May set of wells having been connected to the power plant, moving geothermal brine through the heat exchangers and •Progressed Cape Station's second phase of development, with eight GeoBlocks slated to come online in 2028, be available shortly after the live webcast’s conclusion. 11, 2026, and Fervo’s other filings with the SEC. spinning the turbines. Fervo expects to begin generating test power at GeoBlock 1 in the fourth quarter of 2026, and added a third Helmerich & Payne rig in line with the Phase II development plan. ABOUT FERVO with full production anticipated by year-end. GeoBlocks 2 and 3 are expected to follow a similar sequence, with •Accelerated pipeline maturation, moving eight GeoBlocks (400 megawatts) into Advanced Development In light of these factors, the events anticipated by Fervo’s forward-looking statements may not occur at the time initial power in early 2027 ramping to full power over the ensuing months. while advancing 10.5 gigawatts of capacity potential across two new GeoClusters into Early Development. anticipated or at all. Moreover, Fervo operates in a very competitive and rapidly changing environment, and new Fervo Energy (NASDAQ: FRVO) is a modern power company built around one of the market’s most important risks emerge from time to time. Fervo cannot predict all risks, nor can it assess the impact of all factors on its needs: affordable, dependable new power supply. Through the large-scale deployment of enhanced geothermal Fervo's second phase of development at Cape Station, 400 megawatts across eight 50-megawatt GeoBlocks, business or the extent to which any factor, or combination of factors, may cause actual results to differ materially systems, Fervo has established a repeatable, industrial approach to building utility-scale power. The Company is continues to advance toward its 2028 delivery date, building on the lessons of Phase I. This expansion from those anticipated by any forward-looking statements it may make. Accordingly, you should not place undue transforming geothermal into a clean, reliable, cost-competitive solution designed to meet rising demand from AI incorporates the Company's 3.0 well design, with longer laterals and larger-diameter casing than Phase I, reliance on any forward-looking statements. All forward-looking statements speak only as of the date of this press hyperscalers, utilities, and a more electricity-intensive economy. For more information, visit engineered to increase power output per well while reducing installed cost per kilowatt. During the quarter, Fervo release or, if earlier, as of the date they were made. Fervo does not intend to, and disclaims any obligation to, www.fervoenergy.com. drilled Sawtooth 7, its ninth Fervo 3.0 well, reaching a measured depth of nearly 19,500 feet in a 460°F resource update or revise any forward-looking statements unless required by applicable law. (1) Shares for periods presented have been retroactively adjusted to reflect the 0.7194-for-1 reverse stock split effected on May 14, 2026 in connection with the Company’s initial public offering (“IPO”). See Note 1 - Nature of Business and Note 2 - Significant Accounting Policies for details.