What management said about Q2 FY2026, from the documents filed with the SEC on 28 July 2026: press release. Guidance figures: 4 kept. The quarter’s numbers.

Key takeaways

  • Q2 GAAP EPS $0.50 versus $0.46: GAAP earnings were $288 million, or $0.50 per basic and diluted share, on revenue of $3.7 billion, against $268 million, or $0.46 per share, on $3.4 billion a year earlier. Source
  • Core EPS $0.50 versus $0.52: Core Earnings were $0.50 per share, which the company described as in line with plan, compared with $0.52 in the second quarter of 2025. Source
  • Distribution Core EPS down $0.06: Distribution Core Earnings decreased $0.06 per share year over year, mainly from higher maintenance expenses, which the company said were in line with plan. Source
  • Contracted data center demand 6.4 GW: Contracted and pipeline data center demand rose 30% since the first quarter, with contracted demand at 6.4 GW. Source
  • West Virginia demand up 137%: West Virginia demand rose 137% to 4.3 GW, the company reported. Source
  • Energize365 renews grid infrastructure: The Energize365 program will modernize the grid by renewing distribution infrastructure and strengthening transmission reliability. Source

“We delivered another quarter of solid financial performance, demonstrating the strength of our strategy and our disciplined execution”

Brian X. Tierney, FirstEnergy Board Chairman, President and Chief Executive Officer

Guidance

AreaPeriodFigureAgainst last quarter
Core EPS Source2026$2.62 to $2.82 per shareKept
Core EPS compound annual growth Source2026 to 2030near the top end of 6% to 8%Kept
Capital investment plan Source2026$6 billionKept
Energize365 capital program Source2026 to 2030$36 billionKept

What changed from last quarter

  • Guidance kept: 2026 Core EPS guidance of $2.62 to $2.82 per share was reaffirmed, the same range as the first-quarter release. Source
  • Guidance kept: Long-term Core EPS compound annual growth near the top end of 6% to 8% for 2026 to 2030 was reaffirmed. Source
  • New: The release names the proposed Maidsville Energy Center in West Virginia, which the first-quarter release did not mention. Source

Results and year-to-date

  • Q2 GAAP EPS $0.50 versus $0.46: GAAP earnings were $288 million, or $0.50 per basic and diluted share, on revenue of $3.7 billion, against $268 million, or $0.46 per share, on $3.4 billion a year earlier. Source
  • Core EPS $0.50 versus $0.52: Core Earnings were $0.50 per share, which the company described as in line with plan, compared with $0.52 in the second quarter of 2025. Source
  • First-half Core EPS $1.22: First-half GAAP EPS was $1.20 on $7.9 billion of revenue. Core EPS was $1.22 against $1.19, with regulated investment growth partly offset by planned operating expenses. Source
  • Return on equity 9.5% trailing: Consolidated return on equity was 9.5% on a trailing 12-month basis. Source

Segment results

  • Distribution Core EPS down $0.06: Distribution Core Earnings decreased $0.06 per share year over year, mainly from higher maintenance expenses, which the company said were in line with plan. Source
  • Integrated flat on transmission growth: Integrated Core Earnings were flat. Transmission rate base growth of 22% raised transmission earnings, offset by planned maintenance expenses. Source
  • Stand-Alone Transmission up $0.04: Stand-Alone Transmission Core Earnings rose $0.04 per share, with transmission rate base 11% higher than in the second quarter of 2025. Source

“Increasing customer demand continues to create significant incremental opportunities across our service territory”

Brian X. Tierney, FirstEnergy Board Chairman, President and Chief Executive Officer

Special items and storm response

  • Q2 special items net to zero: Investigation and other related costs of $0.04 per share were offset by pension and OPEB credits of $0.03 and an ARO regulatory change of $0.01. Source
  • Year-to-date special items $0.02: Year-to-date special items totaled $0.02 per share, compared with $0.10 in the first half of 2025. Source
  • Crews restored power after storms: Employees responded to significant heat and storms in parts of the footprint and restored power as quickly as possible. Source

Demand and capital deployment

  • Contracted data center demand 6.4 GW: Contracted and pipeline data center demand rose 30% since the first quarter, with contracted demand at 6.4 GW. Source
  • West Virginia demand up 137%: West Virginia demand rose 137% to 4.3 GW, the company reported. Source
  • $2.9 billion deployed in first half: Capital investments deployed through the first half of 2026 totaled $2.9 billion, against the $6 billion planned for the year. Source

“I am pleased with the substantial growth in contracted data center demand since the first quarter and am excited about what we are seeing in West Virginia”

Brian X. Tierney, FirstEnergy Board Chairman, President and Chief Executive Officer

Strategy and grid investment

  • Energize365 renews grid infrastructure: The Energize365 program will modernize the grid by renewing distribution infrastructure and strengthening transmission reliability. Source
  • Program nearly 30% above prior plan: The company said the five-year program is nearly 30% larger than its previous five-year investment program. Source
  • Demand may raise long-term growth: Management said the trends in customer demand, economic development and new infrastructure needs could raise its long-term investment and earnings growth profile. Source

Investor materials and reconciliation

  • Analyst teleconference July 29: Management will present results and hold a question-and-answer session at 9:00 a.m. EDT on July 29, 2026. Source
  • Special items defined: Special items are described as charges or benefits that management believes are not indicative of ongoing core activities. Source
  • Share count for per-share measures: Basic EPS and Core EPS were based on 578 million shares for the second quarter and first half of 2026. Source

Coming up, as management said on 28 July 2026

  • Maidsville project advancing: The company is advancing the proposed Maidsville Energy Center and evaluating additional generation, transmission and distribution investments. Source

Figures management reported

FigureReported
Rate base growth Sourcetransmission rate base growth 22% (Integrated segment)
Rate base growth Sourcetransmission rate base up 11% versus second quarter 2025 (Stand-Alone Transmission)
Capital plan Source$6 billion in 2026; $36 billion for 2026 to 2030 (Energize365)
Load growth Sourcecontracted data center demand 6.4 GW; West Virginia demand 4.3 GW, up 137%
EPS growth target SourceCore EPS compound annual growth near the top end of 6% to 8%, 2026 to 2030

Risks management discussed

  • External: Significant heat and storms across parts of the service territory required restoration work during the quarter. Source
  • Operational: Higher maintenance expenses were cited as the main reason Distribution Core Earnings declined. Source

Earlier plans management reported on

  • On track: Management said the company remains on track for earnings growth near the top end of its targeted rate through 2030. Source
  • Not stated: Management said the results reinforce confidence in achieving its 2026 commitments. Source
  • On track: The company described second-quarter Core Earnings as in line with plan. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.