Eos Energy Enterprises, Inc.: Q2 FY2026 earnings call

What management said about Q2 FY2026, from the documents filed with the SEC on 5 August 2026: press release. Guidance figures: 1 narrowed. The quarter’s numbers.

Key takeaways

  • Revenue rose 351% year over year: Revenue was $68.8 million, up 351% year over year, driven by 207% higher cube deliveries. Six-month revenue was $125.7 million. Source
  • Net loss driven by fair value swings: Net loss attributable to shareholders was $275.7 million, mainly from mark-to-market fair value adjustments on certain liabilities tied to the end-of-quarter stock price. Source
  • Line 2 cycle times run faster: Line 2 battery cycle times ran about 10% faster and bipolar cycle times about 11% faster than Line 1. Source
  • Consolidation into Thorn Hill under evaluation: Consolidating production into one Thorn Hill footprint is expected to improve efficiency, capacity use and margins; timing is still being evaluated. Source
  • Gross margin improved to negative 71%: Gross loss was $48.8 million, with gross margin at negative 71%, up 132 points year over year and 7 points sequentially. Source
  • Backlog reached record $807 million: Backlog was $807 million, up 25% sequentially and 20% year over year, from four new and two repeat customers. Source
  • Department of War partnership and award: After quarter end, Eos announced a partnership with the Department of War and received a contract tied to Golden Dome for America. Source
  • FPUSA raised $263 million gross: FPUSA raised about $263 million gross from Eos, Cerberus and Hudson Bay, above its $250 million equity target. FPUSA expects access to over $1 billion of project capital. Source

“We delivered more revenue in the first half of 2026 than in all of 2025,”

Joe Mastrangelo, Chief Executive Officer of Eos

Guidance

AreaPeriodFigureAgainst last quarter
Full-year revenue Sourcefiscal year 2026$300 million to $350 millionNarrowed, top end cut from $300 million to $400 million
Energy projects starting operations Sourceby year-end 2026more than 200 MWh
Thorn Hill manufacturing capacityyear-end 20264 GWh annual run-rate capacity

What changed from last quarter

  • Guidance lowered: Full-year 2026 revenue range narrowed; the top end was cut from $400 million to $350 million. Source
  • New: Frontier Power USA joint venture closed on August 4, 2026, after the quarter end. Source
  • New: Subsequent to quarter end, a $100 million purchase order from FPUSA for Phase I of the Blanquilla project was received. Source
  • New: Strategic partnership with the Department of War announced, with a contract supporting the Golden Dome for America initiative. Source
  • New: Binding master supply agreement with CAPAC Energy creates an exclusive distribution partnership in three European countries. Source
  • New: Management is evaluating the timing of moving manufacturing into the Thorn Hill facility; no date is given. Source

Results and growth drivers

  • Revenue rose 351% year over year: Revenue was $68.8 million, up 351% year over year, driven by 207% higher cube deliveries. Six-month revenue was $125.7 million. Source
  • One project supplied 80% of revenue: $55.0 million of revenue came from a pre-existing project financed by a Cerberus affiliate, about 80% of second-quarter revenue. Source
  • Net loss driven by fair value swings: Net loss attributable to shareholders was $275.7 million, mainly from mark-to-market fair value adjustments on certain liabilities tied to the end-of-quarter stock price. Source
  • Adjusted EBITDA loss widened: Adjusted EBITDA loss was $71.4 million, compared with $51.6 million in the prior-year period. Source
  • Cumulative discharged energy passed 6.5 GWh: Cumulative energy discharged by Eos technology rose by nearly half a gigawatt-hour over the past three months. Source

Manufacturing ramp and consolidation

  • Line 2 cycle times run faster: Line 2 battery cycle times ran about 10% faster and bipolar cycle times about 11% faster than Line 1. Source
  • Full automation now online: Site acceptance testing and commissioning were completed across all sub-assembly operations during the quarter. Source
  • Partial shift as ramp continues: Line 2 is running one partial production shift as part of the planned ramp. Source
  • Consolidation into Thorn Hill under evaluation: Consolidating production into one Thorn Hill footprint is expected to improve efficiency, capacity use and margins; timing is still being evaluated. Source

“The market wants a U.S. supplier of long-duration energy storage that can deliver at scale. Our focus now is converting that demand into profitable growth.”

Joe Mastrangelo, Chief Executive Officer of Eos

Costs and margins

  • Gross margin improved to negative 71%: Gross loss was $48.8 million, with gross margin at negative 71%, up 132 points year over year and 7 points sequentially. Source
  • Adjusted gross loss $42.9 million: Adjusted gross loss, which excludes stock-based compensation and depreciation, was $42.9 million. Source
  • R&D rose while SG&A eased: Research and development expenses were $10.5 million, against $7.2 million a year earlier. Selling, general and administrative expenses were $24.5 million, against $25.5 million. Source
  • Adjusted EBITDA margin improved: Adjusted EBITDA margin improved by 235 points year over year and 16 points sequentially, which management attributes to operational efficiencies and higher revenue. Source

Demand and order book

  • Backlog reached record $807 million: Backlog was $807 million, up 25% sequentially and 20% year over year, from four new and two repeat customers. Source
  • One project and FPUSA hold 49%: As of June 30, 2026, the Cerberus-financed project and FPUSA together represented 49% of backlog volume. Source
  • FPUSA pipeline about 16 GWh: FPUSA's development pipeline totals about 16 GWh, with about 5.0 GWh acquired, selected or under active diligence. Source

“The decisions we are making today, including the consolidation of manufacturing into Thorn Hill, are about building a lower-cost operation that can support that demand.”

Joe Mastrangelo, Chief Executive Officer of Eos

Projects, customers and deals

  • Redbird order moved to FPUSA: The first purchase order for the 100 MW / 400 MWh Redbird project, received in the quarter, moved to FPUSA at closing. Source
  • Department of War partnership and award: After quarter end, Eos announced a partnership with the Department of War and received a contract tied to Golden Dome for America. Source
  • CAPAC distribution deal in Europe: A binding master supply agreement with CAPAC Energy covers Germany, Austria and Switzerland, with an initial 750 MWh commitment. Source

Capital, cash and FPUSA funding

  • FPUSA raised $263 million gross: FPUSA raised about $263 million gross from Eos, Cerberus and Hudson Bay, above its $250 million equity target. FPUSA expects access to over $1 billion of project capital. Source
  • Total cash $364.1 million: Total cash including restricted cash was $364.1 million at June 30, 2026; cash and cash equivalents were $305.5 million. Source
  • Operating cash outflow $191.8 million: Net cash used in operating activities for the first six months was $191.8 million, against $95.0 million a year earlier. Source
  • Investing outflow $70.6 million: Net cash used in investing activities for the first six months was $70.6 million, against $12.0 million a year earlier. Source

Coming up, as management said on 5 August 2026

  • FPUSA projects near notice to proceed: About 1.8 GWh of FPUSA projects are under construction or approaching notice to proceed. Source

Figures management reported

FigureReported
Backlog Source$807 million; 3.4 GWh
Cube deliveries growth Source207% higher year over year
Cumulative energy discharged Sourcemore than 6.5 GWh
FPUSA development pipeline Sourceapproximately 16 GWh

Risks management discussed

  • Operational: Temporary manufacturing underutilization during the two-facility ramp, along with higher project costs, partly offset the gross margin gains. Source

Earlier plans management reported on

  • On track: Line 2 launched in mid-June, which management describes as on schedule and in line with prior expectations. Source
  • On track: Management says it remains on track to reach full production capacity in the fourth quarter. Source
  • Not stated: The prior release expected full commissioning of all bi-polar machines in July 2026. The August release does not state whether this was completed on that date.

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.