Key takeaways

  • Revenue rose 85% from prior quarter: Revenue was $12.25 million, up from $6.63 million in Q2 2026 and up 50% from the $8.1 million reported for Q3 2025. Source
  • Net income positive, aided by gains: Net income was $1.0 million, or $0.01 per share, against a net loss of $14.36 million in Q2 2026. Management said digital currency and warrant valuation gains materially supported the result. Source
  • AI revenue reached 46% of total: AI revenue was $5.66 million, more than 400% above Q2 2026 and nil in Q3 2025. It comprises Tier III colocation and GPU rental. Source
  • Legacy bitcoin share fell to 27%: Legacy Bitcoin colocation contributed $3.11 million, 25.4% of revenue. Legacy Bitcoin activities were about 63% of revenue a year earlier. Source
  • Cerebras Phase 1 fees average $40 million: Ten-year take-or-pay colocation agreement with Cerebras. Phase 1 annual fees are expected to average about $40 million over the term. Source
  • Adjusted EBITDA fell from Q2: Adjusted EBITDA was $0.6 million, compared with $3.3 million in the Q2 2026 release. EBITDA was $6.5 million, against a $10.29 million loss in Q2 2026. Source
  • Cash and digital currencies declined: Cash, equivalents and digital currencies were $119.64 million, down $22.78 million from June 30. Working capital was $103.0 million and borrowings were nil. Source

“Our third-quarter results demonstrate that Digi Power X’s transformation into an AI infrastructure company is beginning to take hold.”

Michel Amar, Chairman & Chief Executive Officer, Digi Power X Inc.

Guidance

AreaPeriodFigureAgainst last quarter
Annualized revenue run-rate Sourceend of Q3 2027$250-300 millionKept
Contracted revenue run-rate Sourceduring 2027approximately $143 millionRaised from approximately $140 million
Capital expenditures Source2027approximately $350 millionNew
Columbiana Phase 1 tenant access SourceQ4 2026December 15, 2026Kept
Columbiana Phase 2 tenant access SourceQ1 2027March 2027Kept
Project debt financing SourceQ4 2026currently expected in Q4 2026New
New York site transition SourceQ3 and Q4 2027beginning in Q3 and Q4 2027Kept
North Carolina campus capacity Source2029 and 2030approximately 75 MW in 2029 and an additional 75 MW in 2030Kept
Aggregate power capacity Sourceif development plans are fully realizedover 400 MWNew

What changed from last quarter

  • New: Launched the NeoCloudz Token Factory, selling AI inference directly to customers instead of renting compute at wholesale prices. Source
  • New guidance: The 2027 capital expenditure figure of about $350 million was not in the prior release and appears in this one. Source

Results and growth drivers

  • Revenue rose 85% from prior quarter: Revenue was $12.25 million, up from $6.63 million in Q2 2026 and up 50% from the $8.1 million reported for Q3 2025. Source
  • Net income positive, aided by gains: Net income was $1.0 million, or $0.01 per share, against a net loss of $14.36 million in Q2 2026. Management said digital currency and warrant valuation gains materially supported the result. Source
  • Columbiana billing still ahead: Management said the quarter's revenue was earned before Columbiana colocation billing had started. Source

Revenue mix and segments

  • AI revenue reached 46% of total: AI revenue was $5.66 million, more than 400% above Q2 2026 and nil in Q3 2025. It comprises Tier III colocation and GPU rental. Source
  • Energy sales rose 68% sequentially: Energy sales were $3.29 million, 26.9% of revenue, up 9% from a year earlier. Source
  • Legacy bitcoin share fell to 27%: Legacy Bitcoin colocation contributed $3.11 million, 25.4% of revenue. Legacy Bitcoin activities were about 63% of revenue a year earlier. Source
  • Tier III colocation contributed 26.1%: Tier III colocation services brought in $3.20 million, 26.1% of revenue, and form part of the AI revenue total. Source

“Our next priority is execution: bringing Columbiana into service, expanding our compute capacity and converting our power assets into long-term contracted revenue.”

Michel Amar, Chairman & Chief Executive Officer, Digi Power X Inc.

Columbiana colocation contract

  • Cerebras Phase 1 fees average $40 million: Ten-year take-or-pay colocation agreement with Cerebras. Phase 1 annual fees are expected to average about $40 million over the term. Source
  • Phase 2 adds $58.5 million annually: Phase 2 would add about $58.5 million of annual fees, bringing combined average annual fees to about $107 million. Source
  • Option could lift value to $2.5 billion: An option to extend the relationship for an additional term could raise total potential contract value to about $2.5 billion. Source

GPU rental and Token Factory

  • GPU rental revenue grew 127%: GPU rental revenue rose 127% from Q2 2026 and was nil in the year-earlier quarter. Source
  • Token Factory keeps value of each token: The Token Factory sells AI inference directly. Because the company owns the stack, it keeps the value of each token rather than renting compute at wholesale prices. Source
  • Higher margins expected from token sales: Management expects the Token Factory to add a new revenue stream with meaningfully higher margins. No margin figures were given. Source

“Going live with the NeoCloudz Token Factory is a major step for Digi Power X.”

Alec Amar, President, Digi Power X Inc.

Margins and non-GAAP measures

  • Adjusted EBITDA fell from Q2: Adjusted EBITDA was $0.6 million, compared with $3.3 million in the Q2 2026 release. EBITDA was $6.5 million, against a $10.29 million loss in Q2 2026. Source
  • Gross loss narrowed from prior quarter: GAAP gross loss was $2.41 million, against $5.48 million in Q2 2026. Gross profit before depreciation and amortization was $3.08 million, against a $1.46 million loss. Source
  • Valuation gains removed in reconciliation: The reconciliation removes a $7.1 million crypto revaluation gain and a $1.5 million warrant fair-value gain, and adds back $5.5 million of D&A and $2.2 million of share-based compensation. Source

Cash, balance sheet and capital plan

  • Cash and digital currencies declined: Cash, equivalents and digital currencies were $119.64 million, down $22.78 million from June 30. Working capital was $103.0 million and borrowings were nil. Source
  • Digital currency holdings up 56%: Digital currencies were $24.5 million, up from $15.4 million a year earlier. Source
  • Net fixed assets rose 99%: Net fixed assets were $145.6 million, up from $73.24 million at June 30. Shareholders' equity was $279.9 million. Source
  • 2027 capex funded mainly by deposits: Management intends to fund the program principally through customer deposits and prepayments and debt financing, together with cash on hand. Source
  • Plan designed to limit dilution: Management said capital deployment is tied to contracted revenue and is designed to minimize dilution to shareholders. Source

Development sites and strategy

  • New York sites readied for AI: The company continues to prepare its New York infrastructure assets for conversion to AI data center operations. Source
  • North Carolina site acreage: The company owns about 40 acres beside a large North Carolina switchyard, the base for a planned AI campus. Source
  • West Virginia power asset under review: The company continues to assess its earlier LOI for a 1.3 GW power generation asset in West Virginia. Source

US Data Centers and other holdings

  • Owns 48% of US Data Centers: The company owns about 48% of US Data Centers Inc., which designs ARMS modular AI data center systems, and accounts for it under the equity method. Source
  • URP-1 robotics platform in development: US Data Centers is also developing URP-1, a robotics platform for automated deployment and maintenance of modular data center infrastructure. Source
  • USDC raising outside capital, diluting stake: US Data Centers is raising outside capital for its expansion without capital from or share issuance by the company, which reduces the company's stake. Source

Figures management reported

FigureReported
Columbiana Phase 1 capacity Source15 MW
Columbiana Phase 2 capacity Source25 MW
Contracted value, Phase 1 Sourceapproximately $402 million
Contracted value, both phases Sourceapproximately $1.07 billion
AI inference capacity build-out, 2027 Sourceapproximately 10 MW

Risks management discussed

  • Financial: The proposed $200 million financing may not close on the anticipated terms, on a timely basis, or at all. Source
  • Financial: Phase 2 depends on adequate financing, according to management. Source
  • Financial: The run-rate target depends on financing and market conditions. Source
  • Operational: Phase 2 construction and tenant access depend on several conditions. Source
  • Demand: Part of the run-rate depends on capacity that is not yet under contract. Source

Earlier plans management reported on

  • On track: Management said Phase 1 construction remains on schedule. Source
  • Met: Management refers to the earlier announcement and says the company received the commitment letter for US$200 million of debt financing. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.