Key takeaways

  • Revenue rose, Adjusted EBITDA fell: Revenue of $265.5 million rose $16.1 million, or 6.5%, on the fourth quarter of 2025. Adjusted EBITDA was $28.4 million, down from $36.7 million, and the net loss widened to $47.3 million from $22.2 million. Source
  • Proppant volumes rose sequentially: Proppant sales volumes were 5.7 million tons, about 7.5% above the fourth quarter of 2025, excluding roughly 130 thousand tons of third-party sand bought to meet customer obligations. Source
  • Plant costs rose on Kermit maintenance: Management said severe January weather disrupted West Texas activity and Kermit maintenance cost more than expected, with those costs easing as the quarter progressed. Source
  • Operating cash flow and adjusted free cash flow: Operating cash flow was $19.0 million and adjusted free cash flow $3.8 million, against $22.4 million of adjusted free cash flow in the fourth quarter of 2025. Source
  • Caterpillar framework adds power equipment: Management said access to large natural gas generator sets, which are in high demand and short supply, places Atlas in a stronger position with customers that previously lacked equipment visibility. Source
  • Power business to transform cash flows: Management said the power expansion would completely transform the company's cash flows and create meaningful value for stakeholders. Source

“Our first quarter results were impacted by higher plant operating costs.”

John Turner, President & CEO

Guidance

AreaPeriodFigureAgainst last quarter
Adjusted EBITDA Sourcesecond quarter of 2026approximately $50 millionNew
Power generation capacity deployed Sourcethrough the first half of 2027more than 550 MWNew
Power business scale Sourceby the end of the decadeapproximately 2 GWNew

What changed from last quarter

  • New guidance: Second-quarter Adjusted EBITDA guidance of about $50 million was given; the April 6 release contained no second-quarter figure. Source
  • New: A five-year power purchase agreement for 120 MW was announced with a subsidiary of an investment-grade technology infrastructure provider; the April 6 release did not include it. Source
  • New: The convertible notes offering was completed at $450 million, up from the $300 million base offering with a $45 million option described in the April 6 release. Source
  • New: The Caterpillar Global Framework Agreement, mentioned in the April 6 release, is described here as executed, covering 1.4 GW of incremental generation assets through 2030. Source

Results and growth drivers

  • Revenue rose, Adjusted EBITDA fell: Revenue of $265.5 million rose $16.1 million, or 6.5%, on the fourth quarter of 2025. Adjusted EBITDA was $28.4 million, down from $36.7 million, and the net loss widened to $47.3 million from $22.2 million. Source
  • Margins fell against prior periods: Adjusted EBITDA margin was 11%, against 15% in the fourth quarter of 2025 and 25% a year earlier. Net loss margin was (18%). Source
  • Operating loss widened on lower gross profit: Operating loss was $32.5 million, against $14.9 million in the fourth quarter of 2025, as gross profit fell to $6.3 million from $20.2 million. Source

Segments and service growth

  • Service revenue grew the most: Service revenue rose 10.3% to $139.1 million, the largest sequential gain among the three revenue lines. Source
  • Product revenue rose on proppant: Product revenue rose 3.5% to $108.9 million, the company reported, with proppant sales as the main part of the total. Source
  • Rental revenue declined 3.3%: Rental revenue fell 3.3% to $17.5 million from the fourth quarter of 2025. Source

“Atlas remains effectively sold out for the second quarter and expects volumes to remain elevated for the remainder of 2026.”

John Turner, President & CEO

Products and customers

  • Proppant volumes rose sequentially: Proppant sales volumes were 5.7 million tons, about 7.5% above the fourth quarter of 2025, excluding roughly 130 thousand tons of third-party sand bought to meet customer obligations. Source
  • Power equipment sales were $3.3 million: Product revenue included $105.6 million of proppant sales and $3.3 million of power equipment sales in the quarter. Source
  • Customer focus moved toward data centers: Management said the power customer focus has moved from medium-sized industrial users to data center deployments, which it describes as squarely in the crosshairs. Source

Costs, margins and pricing

  • Plant costs rose on Kermit maintenance: Management said severe January weather disrupted West Texas activity and Kermit maintenance cost more than expected, with those costs easing as the quarter progressed. Source
  • Cost of sales rose 14.3%: Cost of sales rose $26.7 million, or 14.3%, to $214.0 million, excluding depreciation, depletion and accretion expense of $45.2 million. Source
  • Cost of sales by line: Proppant plant costs were $74.7 million and service costs $127.0 million; power equipment costs were $2.1 million, rental costs $5.9 million and royalties $4.3 million. Source
  • SG&A rose 5.9%: Selling, general and administrative expense rose $2.0 million to $35.7 million, or 5.9%, from the fourth quarter of 2025. Source

“We now have surety of supply and scale to become a critical player in the fast-evolving private grid space.”

Bud Brigham, Executive Chairman

Demand and order book

  • Commodity backdrop improved rapidly: Management said the underlying commodity environment improved quickly during the first quarter, which it links to the company's current volumes. Source
  • Volumes expected elevated through 2026: Management expects sales volumes to stay higher than normal for the rest of 2026, after the company was sold out for the second quarter. Source

Capital, cash and liquidity

  • Operating cash flow and adjusted free cash flow: Operating cash flow was $19.0 million and adjusted free cash flow $3.8 million, against $22.4 million of adjusted free cash flow in the fourth quarter of 2025. Source
  • Liquidity totaled $89.5 million: Total liquidity at March 31, 2026 was $89.5 million: $39.8 million of cash and $49.7 million available under the 2023 ABL Credit Facility. Source
  • Maintenance capex rose to $24.6 million: Maintenance capital expenditures were $24.6 million, up from $14.4 million in the fourth quarter of 2025. Source
  • Current debt rose to $65.6 million: The current portion of long-term debt rose to $65.6 million from $40.7 million at December 31, 2025. Source

Strategy and power investment

  • Caterpillar framework adds power equipment: Management said access to large natural gas generator sets, which are in high demand and short supply, places Atlas in a stronger position with customers that previously lacked equipment visibility. Source
  • Power business to transform cash flows: Management said the power expansion would completely transform the company's cash flows and create meaningful value for stakeholders. Source
  • Private grid positioning and presence: The executive chairman said the company is making its presence known to investors and to customers facing grid constraints in Texas and the United States. Source

Figures management reported

FigureReported
Proppant sales volumes Source5.7 million tons
Purchases of property, plant and equipment Source$29.3 million
Maintenance capital expenditures Source$24.6 million
Dividends SourceNone in the first quarter of 2026
Proppant plant operating costs Source$74.7 million

Risks management discussed

  • Operational: Power generating equipment is already in short supply, which management cites as a constraint on the power business. Source
  • External: Severe January winter weather disrupted West Texas oilfield activity, according to management. Source
  • Operational: Maintenance at the Kermit facility cost more than the company originally expected. Source

Earlier plans management reported on

  • Met: Adjusted EBITDA of $28.4 million was reported as in line with the previously announced range. Source
  • Not stated: Management said plant costs fell as the first quarter progressed and expects improved plant operating costs in the second quarter. Source

Other quarters

Summarised with AI from the documents the company filed with the SEC. Every point is checked against the filing before it is shown: management’s own words word for word, figures against the line or table row they come from. A point that fails the check is left out. Source opens the filing at that line.